hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
3:41 am, Saturday, October 17, 2026
53°F
80 %
Wind Gust: 25 mph
Clouds: 100%
Sunrise: 7:00 am
Sunset: 6:01 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Conservation Commission votes not to issue new building permits for Newbury Glen after latest violation

by | May 14, 2025 | Featured: News, News

The Conservation Commission on Tuesday night voted 4-0 to not issue new building permits for the Newbury Glen subdivision until pending improvements are made after the latest in a series of violations was discussed with project representatives.

Newbury Glen, previously called Elmwood Farms III, is located off Blueberry Lane. It incurred three violations in July and August 2023, which led to an enforcement order that September. Another violation occurred in December 2024, and more recent stormwater violations there were discussed in March.

Conservation administrator Judy Day said she observed “significantly turbid water” leaving the off-site basins there on May 9. Silty runoff was flowing to resources downstream, causing concern.

This situation was different from previous violations because it appeared that there was “some kind of blowout in the pipe” that leads from the main basin into a channel that conveys water to a smaller basin further downstream, she added. On the day of the meeting, Day saw water being pumped out of the larger basin into a dewatering bag.

Rich Kirby, the consultant from LEC Environmental for Toll Brothers, the developer, said he met with the new contractor on May 12 to discuss the situation. The previous contractor, who was working on the project when the older violations occurred, was fired.

He said there appeared to be “some issues with the grout and sealing of the pipe that occurs between this pondage and the drain manhole.” This allowed water to bypass a valve and it “excavated a void,” allowing dirt to enter the system. He deemed it “an episodic event.”

The contractor was in the process of pumping the water out of the main stormwater basin, Kirby explained. He hoped repairs could be made within the next four weeks, depending upon the weather.

Newbury Glen stormwater management violations

These photos provided by the town show some of the issues at the Newbury Glen construction site.

Moving forward, Kirby discussed several “preventive measures” that will be implemented. Five 18-inch coir log check dams will be installed near the main basin. Floc logs will be placed at the manhole outlet pipe, while the smaller basin’s outlet will be plugged with an outlet that has a bypass. There also will be a “much more significant check dam” of about 30 feet installed at the smaller basin, where coir logs will be put in place for the duration of the construction period.

Said Kirby: “We want this to last and be formidable when protecting these downstream resources.”

Co-vice chair Matt Moyen, who chaired the meeting, was pleased that measures were being taken to safeguard the downgradient area. He noted that there is very shallow groundwater in this part of town. But he raised the concern of losing basin volume by continuing to store water in them.

Kirby replied that the check dams are intended to slow the movement of water rather than impede it. The second basin would allow water to be held back “if we need to.”

Moyen stressed the history of violations on the project. He said it did not appear that the basins were being “dewatered on a consistent basis.” The larger basin should be the “last line of defense.”

Another issue Moyen raised is that much of the land isn’t currently being built upon. The general permit issued called for “temporary permanent stabilization after 14 days.” Moyen also noted the lack of dewatering bags on-site.

Kirby noted that water has been running across the site down from the location of the middle and high schools. There are catch basins behind the house lots that are working to catch it.

“There have been substantial improvements since I’ve seen it [on] day one,” said Moyen. “But source control has been lacking all along. And without source controls, it’s going to be a continuous battle.”

Co-vice chair Ted Barker-Hook said that he was happy that a new contractor is working on the project. But he was critical that it took several weeks for this contractor to act on a violation meeting notice.

“Why has it taken another violation meeting to realize that all this dirt is still exposed, even though we have the new, better contractor who’s supposed to be better at these things?” he asked.

He then stressed that the commission had asked “two months before” for the sites not being worked on to be stabilized, and no action has been taken yet.

Replied Kirby: “It all takes time.”

“I’ve been sitting here utterly frustrated that this is a continuing episode,” said member Ed Harrow, questioning management decisions.

Moyen said he was “cautiously optimistic” about the new contractor. But until the stabilization methods are implemented, he recommended the withholding of all new building permits.

Baypath animal shelter moves forward

An order of conditions was approved 4-0 for the installation of utilities for a proposed animal shelter at 66-66B Fruit Street.

After a decade-long effort, Baypath Humane Society of Hopkinton, which runs a shelter on Legacy Farms North Road, will be able to move forward with its plan to construct an animal shelter. Day explained that since the last meeting, a file number from the state’s Department of Environmental Protection was received. The applicant also added a line of permanent immovable barriers in between the gravel drive and the wetland to the plans at the commission’s request.

1 Comment

  1. Caroline Lockhart (homeowner at 35 Blueberry Lane)

    Water is higher than this, as of May 27th 2025. (In water basin by 38 Blueberry Lane.) Water is now at the top of this concrete drain. Please send a committee member to view as all these trees will most likely die. What a mess. We hear pumps going on all day and into the evening and yet the water levels are still very high. Shockingly high. Our roads are also being damaged by all these trucks. Damage can be seen on the roads on Ash Street too.

Related Articles

CPC kicks off FY 28 funding cycle with review of requests

The Community Preservation Committee on Thursday opened its hearing for funding requests for the upcoming fiscal year, noting that money is tighter than in the past. “We have probably more requests than what money is going to come in this year,” said chair Ken...

Center School

Parks & Rec submits updated Pyne Field design for CPC funding

Acknowledging it would need to adjust the request upon further review, the Parks & Recreation Commission on Tuesday voted to submit a $3 million Community Preservation application for a new Pyne Field design. Per diem Parks & Rec Director Jon Lewitus...

Pyne Field

Arrests/Police Log, Oct. 14 edition

ARRESTS Oct. 8 6:20 p.m. Officers received a report of a hit and run on a Pendulum Pass mailbox. A vehicle was stopped, and officers conducted a field sobriety test. A 41-year-old man from Whitinsville was arrested and charged with leaving the scene of property...

Hopkinton police cruiser

EDAB seeks clarity on language around economic development plan

The Economic Development Advisory Board on Tuesday discussed the economic development plan presented at the Oct. 6 Select Board meeting, questioning whether its purpose was as a recommended report or a document to be enacted. Camille Jonlin, the Metropolitan Area...

Welcome to Hopkinton sign

Main Street hydrant test Wednesday could cause water discoloration

The Water-Sewer Department will perform a required hydrant flow test on Main Street Wednesday, according to a notice from the Water-Sewer Department. According to the notice, the flow test is scheduled to take place at 48-52 Main Street — the former site of...

Fire hydrant
Key Storage 4.14.22