hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
8:07 am, Friday, March 27, 2026
44°F
80 %
Wind Gust: 12 mph
Clouds: 100%
Sunrise: 6:37 am
Sunset: 7:05 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





ESBC approves upgrades to Charleswood air units, rejects large mock-up for testing

by | Sep 25, 2024 | Education, Featured: Education, Uncategorized

The Elementary School Building Committee at its Tuesday meeting approved rooftop unit upgrades corresponding with accommodations for future expansions to the Charleswood School.

Factored in the project’s design is space for 18 additional classrooms, which would be added on to the ends of each wing. The upgrade increases the capacity of air movement from 24,000 cubic feet per minute (CFM) to 32,000 CFM.

Jeff D’Amico, vice president and project director at Vertex, said upgrading the mechanical equipment for $275,000 now would be less costly than paying an estimated $360,000 plus escalation if the work is done at the time of expansion.

He said the larger unit operates at a lower speed, potentially increasing its life expectancy compared to adding stand-alone 3,000 CFM outside air units in the future.

Elementary School Building Committee (ESBC) member Mike Shepard said he was concerned that 10 years from now, the town could end up paying twice if some new technology has evolved by then.

But Dan Colli, project manager at architect Perkins Eastman, said outside air unit technology had not significantly changed over the past 30-40 years.

D’Amico noted the district already had made a commitment to geo thermal energy and “this (alternate) capitalizes on that investment.”

ESBC member Bill Flannery asked about enrollment projections and when the district expects it could exceed the 1,200 students for which Charleswood School is being built.

Assistant Superintendent Susan Rothermich said the student population has been growing more than 100 students year after year, and the town continues to have development and families with kids moving in.

Rothermich said she and Superintendent Carol Cavanaugh “got comfort” from the fact that separate enrollment projections by the Massachusetts School Building Authority (MSBA) and Arthur Wagman are very similar.

Cavanaugh said it is unlikely the district will gain 212 students just in Grades 2-4 over the next few years, but eventually it could happen.

D’Amico noted MSBA enrollment projections are at 1,223 students in 2029 and 1,300-plus by 2032.

He clarified that this unit is for “fresh air,” and the plans already have capacity for additions with their heat and cooling components.

D’Amico said there is funding available within the construction budget, which is running $1.2 million under budget at around $123.7 million.

The committee voted unanimously to include the rooftop unit upgrades in the construction plans.

Large building mock-up suggested

The board, however, did not agree to a second “alternate” presented — a six-sided, 10-foot-by-10-foot building mock-up used for performance testing. D’Amico said a larger mock-up would be comprised of all the same features and materials of the new school — including roof, masonry, windows, etc., and could be kept after testing for storage or as a wellhead. The cost would be $85,000 to $103,000.

Shepard said it would be “just crazy” to locate that size mock-up structure where it could be prominently seen as people enter the school site.

He said it would be “God awful, ugly and awkward.”

D’Amico said designers would at least like to have a two-sided, L-shaped mock-up structure, and certain performance tests could be done on the school building itself.

D’Amico said he would write to the commissioning agent, who is the person advocating for the larger mock-up. Ultimately, the decision rests with the EBSC, he added.

Board members spoke in favor of adding more oversight and spot-checking during construction instead so that pressure and other tests on the main building are successful.

In other business, the ESBC gave the go-ahead for the 60% construction documents to be submitted to the MSBA.

Tweaks made to design

The board heard a presentation by Robert Bell, education programmer at Perkins Eastman, highlighting slight changes that were made since the last design review.

These tweaks included a slight field location shift, revised crosswalks with added flash signals, reduction of light poles to 15 feet, reconfiguration of small mechanical rooms, removal of one of 15 staff toilets, and minor furnishing revisions.

Bell said his team would be using long and narrow bricks of different colors for the building exterior that “don’t look thick and clunky” and are “more tactile and accommodating for students at the ground level.”

The next ESBC meeting will be Tuesday, Oct. 8, at 6 p.m.

1 Comment

  1. KT

    “D’Amico noted MSBA enrollment projections are at 1,223 students in 2029 and 1,300-plus by 2032.” Keep in mind that the MSBA projected that we would have 1,118 students in grades 2-4 this year. The Superintendent stated we have 985 today. The projections were off by 133 students or 6 entire classrooms. Why do we continue to use this faulty data from MSBA as a basis for determining our space needs, and the resulting massive capital expenditures?

Related Articles

Schools Notebook: Local collegians recognized for accomplishments

Syesha Sen was named to the dean’s list for the fall semester at Northeastern University’s Khoury College of Computer and Information Sciences. … Madalyn Schofield was named to the dean’s list at the University of Maryland, where she is a freshman. … At the...

Boston College

Legislators explain federal impact on state budget to Select Board

https://www.youtube.com/watch?v=sthBQAyvGa4 State Senate President Karen Spilka and Rep. James Arena-DeRosa appeared before the Select Board on Tuesday to discuss the state budget and their legislative wins for Hopkinton constituents. Spilka explained that the...

Town Hall

ESBC members discuss abutters’ concerns about Charleswood work

Elementary School Building Committee members on Tuesday spoke about recent conversations with neighbors regarding what Vertex managing director Jeff D’Amico called “hiccups” near the Charleswood School project site. ESBC chair Jon Graziano said it seemed like an...

Charleswood School construction entrance

HHS students win science awards

A number of Hopkinton High School students won awards at the Worcester Regional Science and Engineering Fair, which was held March 6 at Worcester Polytechnic Institute. Arjun Mehta and Sahaj Pogula received a third-place award for their project, “How Does Applying...

HHS science fair

Schools Notebook: Local collegians recognized

Tufts University’s dean’s list for the fall semester includes five Hopkinton residents: junior Anjali Batra, sophomores Bableen Gill, Lulu Jerrett and Nicole Mousad, and freshman Kayleen Tang. … Earning spots on the dean’s list at Holy Cross were seniors Isabella...

Boston College

HHS group spreads awareness about endometriosis

One in 10 women suffer from endometriosis, and it typically takes 7-10 years to diagnose. Those statistics were enough to prompt a group of Hopkinton High School students to launch a community awareness campaign about the topic. The project is featured as part of...

HOSA students
Key Storage 4.14.22