Main Street Corridor Project update: Undergrounding of services progresses

by | Dec 20, 2024 | News

The town’s latest Main Street Corridor Project update released Friday shared that the transfer of services from the existing overhead systems to the new underground systems continues to make progress.

Crown Castle has completed its work, and as of Dec. 16, Eversource has transferred all but three properties to its new underground system. The town continues to coordinate with Dagle Electric and Eversource to schedule the remaining cut-overs for Eversource.

The town recently completed a walk of the project with Verizon and Comcast as those utilities follow Eversource for cutting over their overhead services to their new underground systems. Comcast is expected to start its work soon.

The town’s goal is to continue to coordinate with the utilities so that all the existing utility poles scheduled to be removed from Wood Street to Ash Street and all the overhead wires from the Police Station to Ash Street are removed as soon as possible.

Weekly construction advisories will resume when there are weekly updates on the project. Until then, the town will send project updates as needed.

This schedule may change due to weather and existing conditions found while performing these tasks. This work may impact traffic and require lane and sidewalk closures, limiting access to driveways and entrances to businesses. Detours and alternating traffic patterns may be used as necessary.

1 Comment

  1. Stan Pulink

    Looks like we are headed into year 5 of a 3 year project.

Related Articles

Claflin Place final paving scheduled for Tuesday

The town announced on Friday that work on final paving on Claflin Place will begin early next week.Contractors will be on site Monday to do pavement repairs and prep work ahead of paving on Tuesday. They will return for another half day of work later in the week to...

Claflin Place construction

DPW to continue roadwork through early August

The Department of Public Works announced it will continue roadwork through the end of this month and into the beginning of August. Work hours are approximately 7 a.m.-5 p.m., during which residents are asked not to park along the sides of the affected streets....

Hayden Rowe roadwork

Police issues dominate Select Board meeting

  https://www.youtube.com/watch?v=cht60I7vtIg The Select Board on Tuesday heard concerns about the Hopkinton Police Department’s use of Flock cameras to capture license plate and vehicle data. It also learned about the progress made by the committee in charge...

Hopkinton Police Station
Key Storage 4.14.22