According to the latest update on the Main Street Corridor Project released Friday, A.F. Amorello & Sons has finished paving the west end of the project.
Amorello will return on site next week to finish winter cleanup. After that, the company will remain offsite for the winter.
Additional paving will continue after the Boston Marathon next year. the Massachusetts Department of Transportation and Amorello will schedule paving for the east side of the project and the intersection of Route 135 and Route 85.
Weather and other existing conditions may change the projected work schedule. For the most up-to-date information, visit the town’s project website at hopkintonmainstreet.com.