hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
6:22 am, Wednesday, July 22, 2026
69°F
95 %
Wind Gust: 5 mph
Clouds: 100%
Sunrise: 5:29 am
Sunset: 8:15 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: Work progresses on both ends of corridor

by | Sep 27, 2024 | News

The town’s latest Main Street Corridor Project update released Friday noted that work will continue on both ends of the corridor.

Brick strip installation by A.F. Amorello & Sons, the project’s construction company, will continue during the upcoming week on the east side of the project. Meanwhile, overhead utility line transfer work will continue on the west side of the project. Electrical line connections may begin to be made.

Eversource crews will continue performing the preliminary work associated with the transformers. All 12 transformers have been installed. Shifting power lines from being overhead to underground is expected to begin in early October.

This schedule may change due to weather and existing conditions found while performing these tasks. This work may impact traffic and require lane and sidewalk closures, limiting access to driveways and entrances to businesses. Detours and alternating traffic patterns may be used as necessary.

0 Comments

Related Articles

Water main on Hayden Rowe Street to shut down Wednesday morning

A portion of the water main on Hayden Rowe Street will be shut down Wednesday morning, according to the Water-Sewer Department. In a notice to residents, Water-Sewer Manager Jed Fenneuff stated that a water main on Hayden Rowe Street will be shut down from 9 a.m.-1...

Fire hydrant on Pleasant Street

Ramp closures at I-90/I-495 interchange planned for Wednesday

The Massachusetts Department of Transportation will close two ramps at the Interstate 90/Interstate 495 interchange in Hopkinton Wednesday night to facilitate construction operations. Both the I-90 eastbound ramp to I-495 northbound (Exit 106) and the I-495...

MassDOT logo

Main Street Corridor Project update: Subdrain work continues

A.F. Amorello & Sons will be back next week to continue installing a subdrain, according to the latest Main Street Corridor Project update. The subdrain is being installed on the north side of Main Street between the driveway of 7 Main Street (east of the...

Road work sign
Key Storage 4.14.22