hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
5:32 pm, Tuesday, September 22, 2026
59°F
58 %
Wind Gust: 11 mph
Clouds: 16%
Sunrise: 6:33 am
Sunset: 6:44 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Planning Board approves stormwater management permit for 87 Hayden Rowe Street office building

by | Oct 17, 2023 | Featured: News, News

The Planning Board at its half-hour meeting Monday night voted 5-0 to approve a stormwater management permit for a two-story office building at 85R and 87 Hayden Rowe Street, allowing the redevelopment project to move one step closer to approval.

The property is next to the Hopkinton Public Schools administration building and across from the middle school. The proposed office building will replace an unoccupied apartment building, which will be demolished. The new building will retain the historic architectural characteristics of the previous structure. The site plan for the office building was first reviewed by the Planning Board in August and approved on Sept. 11.

Daron Kurkjian, the town’s engineering consultant from Weston & Sampson, explained that the developer has addressed his comments in the peer review. They included minor updates to plan specifications, increasing the size of the storm sector unit, and not placing snow in the area where rain gardens are proposed. Site lines for vehicles entering and exiting the parking lot also must be maintained.

Project manager Dave Marquedant confirmed that “some minor adjustments” were made to address the comments by Kurkjian.

Member Ron Priefer chaired the meeting in the absence of chair Gary Trendel and vice chair Rob Benson. He outlined several conditions that were attached to the approval. They included references to erosion and sediment control, as well as a requirement for a long-term operation and maintenance plan. Efforts to mitigate construction-related impacts such as pollution, erosion and land disturbance must be implemented. Permanent seeding can take place beginning in the spring. Prior to the start of construction, a detailed construction sequence plan must be submitted to Principal Planner John Gelcich.

The board continued the decision deadline until Oct. 30 in order to get a signature from Trendel.

Permit requests for 188-190 Fruit Street withdrawn

Earlier in the day, applicant Rebel Hill LLC contacted the Planning Board to withdraw its request for stormwater management and earth removal permits for its revised plans for 188 Fruit Street, which is near the Hopkinton Country Club. The request was approved 5-0.

The original scope of the project was for single-family homes to be built at 188 and 190 Fruit Street. The Planning Board and the Conservation Commission each expressed concerns about the grading of the land, poor soil quality and the amount of land disturbance the development of two homes would cause.

In response, the developers came back with a proposal for one home on the 188 Fruit Street lot. At the Oct. 10 Conservation Commission meeting, board members said they would be more amenable to a proposal that would put the house on both lots and further away from wetlands.

Gelcich explained that because the request was withdrawn without prejudice, “the developer could reapply with the same application within two years.”

0 Comments

Related Articles

Cemetery Commission decides not to apply for CPC funding

The Cemetery Commission on Monday decided not to apply for Community Preservation Act funding via the Community Preservation Committee because it has not yet spent its previous grant awards. Under the CPA, at least 10% of the funding raised must be allocated among...

Mike Whalen

Crews to repave, stripe section of Hayden Rowe Street

The Department of Public Works announced that J.H. Lynch & Sons will be out on Hayden Rowe Street starting Monday to complete road work. According to a notice sent by the DPW, crews conducted paving on Monday between 136-149 Hayden Rowe Street northbound and...

Charleswood Dirt

Main Street Corridor Project update: Work planned for drain manhole

Tasks for the Main Street Corridor are light for the next week, according to the latest update from the town. The main project listed for next week is work on a drain manhole at 63 Main Street. Crews will be completing miscellaneous work throughout the project as...

Road work sign

New I-90/I-495 ramp to open Saturday, overnight closures to continue

According to the latest update from the Massachusetts Department of Transportation, a new ramp at the Interstate 90/Interstate 495 interchange in Hopkinton is scheduled to open Saturday. A new I-90 westbound ramp to I-495 northbound is set to open Saturday morning....

MassDOT logo

Final preparations underway for Family Day

Organizer Pat O'Brien is optimistic about this Saturday's Hopkinton Family Day. "The weather's going to be nice," said O'Brien. "That's the main thing we're looking for." The Friends of Hopkinton, which organizes and runs Family Day annually, has been putting final...

Family Day fireworks
Key Storage 4.14.22