Main Street Corridor Project update: Comcast cut-over service delayed, anticipated to complete this month

by | Jul 18, 2025 | Featured: News, News

The town’s latest Main Street Corridor Project update released Friday shared that a delay in services has pushed back cut-over work by Comcast, while AT&T still is on track to complete work by mid-July.

Verizon is expected onsite next week to transfer current equipment on poles, place new fiber and remove old poles. An anticipated completion date has not yet been provided.

A.F. Amorello & Sons is anticipated to mobilize fully once the utility work is complete. The construction company will assist Dagle Electric with utility work at the corner of Meserve Street and Main Street on Thursday.

Finally, the Massachusetts Department of Transportation is reviewing additional landscaping changes to the project. Comments will be sent to the town and Amorello upon completion.

Weather and other existing conditions may change the projected work schedule. For the most up-to-date information, visit the town’s project website at hopkintonmainstreet.com.

0 Comments

Related Articles

Private road policy dominates Planning Board meeting

https://www.youtube.com/watch?v=W-IXUu0T-T0 Private ways and the town’s policy for accepting them as public roads were the main focus of the Planning Board’s three-hour meeting Monday night. The first private road discussed was Morse Lane, which was approved as a...

Morse Lane

Main Street Corridor Project update: Trench, test pit planned

Several tasks related to the Main Street Corridor Project have been scheduled for the coming week, according to the latest project update. Workers will be digging a test pit at the manhole in the driveway of Hillers Cleaners on Monday. Access may be limited. The...

Road work sign

Hopkinton Drug site water main work canceled

Water-Sewer Manager Jed Fenneuff informed residents on Thursday that a water service interruption at the former Hopkinton Drug site planned for Monday has been canceled. "Due to recent design modifications for the 52 Main Street project, overnight water main work...

HopDrug Progress

Lake Maspenock herbicide treatment scheduled for Tuesday

The town announced this week that it will conduct herbicide treatments at Lake Maspenock to control "nuisance aquatic vegetation" on Tuesday. During and following treatment, residents are advised not to use the lake for recreation or agricultural purposes for a...

Maspenock weed survey

Parks & Rec hears tree removal plan for path to EMC Park

A plan to remove trees at EMC Park will go to the Select Board for a vote following public objections at a hearing with the Parks & Recreation Commission on Tuesday. Department of Public Works Director Kerry Reed and Dave Daltorio, the town engineer, met with...

EMC playground sign
Key Storage 4.14.22