Charleswood School project continues ahead of schedule

by | Nov 18, 2026 | Education, Featured: Education

During a brief meeting of the Elementary School Building Committee on Tuesday, members got updates on work progress, the budget, the schedule and next steps.

Chris Kenney, project manager at Vertex, reported the $158 million project remains ahead of schedule, with substantial completion expected on July 1, 2027, and final completion/ready for students by Aug. 27, 2027. (The contract has that date as Jan. 3, 2028).

Kenney noted expenditures to date on the project are at 71% or $87,426,385, while commitments to date are at 78% or $122,829,368.

When asked what is not yet included in the amount of commitments to date, Kenney replied those items mainly consist of furniture, fixtures and equipment (FF&E) along with computers and technology. He said a further update will be provided in January or February.

Project director Chris Eberly, also of Vertex, noted that utility costs including Verizon services as well as moving expenses also need to be factored in to the commitments.

“That’s going to be for the complexities of the move between multiple buildings,” Eberly said.

He was referring to moving sixth graders from Hopkinton Middle School to Hopkins School, moving Hopkins fourth graders to Elmwood School, then taking everything needed from Elmwood School to Charleswood School.

Eberly said based on the Hopkins project move, an average of 16 crates per classroom would be transferred, with the plan to get dumpsters and leave behind things that are unnecessary.

Eberly said he expects to bring a person on board to coordinate logistics and ensure that the transitions between buildings go smoothly.

ESBC member Bill Flannery asked what would happen to the desks and chairs from Elmwood that are being replaced for the Charleswood School. He wondered if there was an opportunity to recoup money from them.

Eberly replied that based on Vertex’s experience with other school projects, old furniture rarely gets sold — noting it is “usually worn” and varies from school to school.

However, one option is to declare it as surplus and post about its availability so other towns can acquire it, he said.

Calling Elmwood School “a town resource,” Eberly added there is no reason to get rid of its furnishings until Hopkinton decides how the building will be used.

Charleswood School will be furnished with all new items, Eberly said.

At the end of November, a request for proposals (RFP) for technology will go out, according to Kenney. He added that user groups are looking at various options for desks and chairs for both teachers and students.

In other business, Kenney highlighted some of the work being done, including the installation of an elevator, which he called “a major milestone.”

Other work progressing, he said, included paving at the front entry drive; installation of a stormwater detention system; water service entry piping; heating, ventilation and air conditioning (HVAC) equipment installation; curtain wall glazing and more.

The ESBC also approved this month’s invoices totaling $5.8 million.

0 Comments

Submit a Comment

Your email address will not be published. Required fields are marked *

Related Articles

School Committee approves capital plan

During a brief Zoom meeting Friday, the School Committee unanimously approved a revised fiscal year 2028 capital plan that includes requests totaling $545,000 as well as $22.4 million for a geothermal heat, ventilation and air conditioning system at the high...

Hopkinton Public Schools Administration sign

Health survey of local students shows encouraging trend

Hopkinton’s middle and high school students are feeling less anxious and depressed, but there still are areas of concern, particularly for students with disabilities and in the LGBTQ+ community. At this past Thursday's School Committee meeting, the results of the...

Hopkinton Middle School

FY 28 capital plan outlined for school district

School Committee members on Nov. 12 are expected to vote on a capital plan for fiscal year 2028, with Town Meeting next May to determine authorization of funds. At this past Thursday's meeting, Assistant Superintendent/Chief Operating Officer Jeff LaBroad outlined...

Hopkinton High School

ESBC OK’s temporary roadwork, discusses stormwater issues

The Elementary School Building Committee on Tuesday night approved a budget change of $200,769 related to temporary paving and a berm on Hayden Rowe Street related to the Charleswood School project. The payment reflected a pivot taken in response to the utility...

Charleswood Dirt

School Committee reviews school improvement plans

https://www.youtube.com/watch?v=-odK9fHCCTg The School Committee on Thursday learned the details of each school’s improvement plan, their common focus on student support and leadership, and an emphasis on the English language arts curriculum. Before the series of...

Hopkinton Public Schools Administration sign

School Committee chooses firm for enrollment study

https://www.youtube.com/watch?v=NVWIDtMIhzM&list=PL8WekT6kxX1B3xlP6fIr3QmhJButK4GkU&index=1 The School Committee on Thursday awarded a $15,750 contract to FutureThink, LLC to conduct an enrollment study and forecast spanning 2027 to 2031. Cynthia D. Mahr,...

Hopkinton Public Schools sign
Key Storage 4.14.22