During a brief meeting of the Elementary School Building Committee on Tuesday, members got updates on work progress, the budget, the schedule and next steps.
Chris Kenney, project manager at Vertex, reported the $158 million project remains ahead of schedule, with substantial completion expected on July 1, 2027, and final completion/ready for students by Aug. 27, 2027. (The contract has that date as Jan. 3, 2028).
Kenney noted expenditures to date on the project are at 71% or $87,426,385, while commitments to date are at 78% or $122,829,368.
When asked what is not yet included in the amount of commitments to date, Kenney replied those items mainly consist of furniture, fixtures and equipment (FF&E) along with computers and technology. He said a further update will be provided in January or February.
Project director Chris Eberly, also of Vertex, noted that utility costs including Verizon services as well as moving expenses also need to be factored in to the commitments.
“That’s going to be for the complexities of the move between multiple buildings,” Eberly said.
He was referring to moving sixth graders from Hopkinton Middle School to Hopkins School, moving Hopkins fourth graders to Elmwood School, then taking everything needed from Elmwood School to Charleswood School.
Eberly said based on the Hopkins project move, an average of 16 crates per classroom would be transferred, with the plan to get dumpsters and leave behind things that are unnecessary.
Eberly said he expects to bring a person on board to coordinate logistics and ensure that the transitions between buildings go smoothly.
ESBC member Bill Flannery asked what would happen to the desks and chairs from Elmwood that are being replaced for the Charleswood School. He wondered if there was an opportunity to recoup money from them.
Eberly replied that based on Vertex’s experience with other school projects, old furniture rarely gets sold — noting it is “usually worn” and varies from school to school.
However, one option is to declare it as surplus and post about its availability so other towns can acquire it, he said.
Calling Elmwood School “a town resource,” Eberly added there is no reason to get rid of its furnishings until Hopkinton decides how the building will be used.
Charleswood School will be furnished with all new items, Eberly said.
At the end of November, a request for proposals (RFP) for technology will go out, according to Kenney. He added that user groups are looking at various options for desks and chairs for both teachers and students.
In other business, Kenney highlighted some of the work being done, including the installation of an elevator, which he called “a major milestone.”
Other work progressing, he said, included paving at the front entry drive; installation of a stormwater detention system; water service entry piping; heating, ventilation and air conditioning (HVAC) equipment installation; curtain wall glazing and more.
The ESBC also approved this month’s invoices totaling $5.8 million.