hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
5:38 pm, Tuesday, September 22, 2026
59°F
58 %
Wind Gust: 6 mph
Clouds: 58%
Sunrise: 6:33 am
Sunset: 6:44 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Eversource introduces proposed underground cable modernization project that will impact South Street

by | Mar 21, 2024 | News

Representatives from Eversource hosted a virtual open house Tuesday to introduce Hopkinton and Milford residents to its proposed underground cable modernization project.

The session is the beginning of Eversource’s outreach to gather community feedback. The project involves the replacement of two high-pressure gas filled (HPGF) lines with modernized cross-linked polyethylene (XLPE) technology. The replacement will follow the same or similar route of the existing HPGF lines, which run a 1.3 mile route between a portion of South Street in Hopkinton through to Purchase Street in Milford between the two existing substations.

Eversource project manager Ian Kea, who led the presentation, explained that the existing 126-501/502 HPGF electric transmission lines in Hopkinton and Milford were installed in 1998, and they are among the last remaining HPGF lines in operation within the system.

This proposed project is part of a larger Eversource program to modernize cables throughout its service territory in Massachusetts and Connecticut. Replacing these lines aligns with the state’s goal to achieve net carbon emissions standards by 2050. It will also help accommodate the increased demand for power.

Kea said the work will not disrupt normal electrical service to customers.

Construction is scheduled to start in the fall of 2025 and be completed in two years, pending necessary approvals. But the timeline is uncertain because of permitting issues that potentially could delay the project by as much as 18 months.

One reason for replacing the lines is that there is limited manufacturing of existing cable lines. The XLPE cables are wider to meet future energy demands.

Eversource representative Allie Klein explained that the lines “allow us to provide larger amounts of power between our substations.”

The project will involve the installation of six vaults, which is expected to reduce the need for future street excavation. Trenching will be performed to install the vaults and new manholes.

“This project will require a completely new duct bank and manhole system,” Klein said. “Technology at each splice point requires a separate duct bank for each line. This will both facilitate cable installation and allow for additional access points for future maintenance, repair work or any inspections that are required.”

“It’s important to note that not all of this happens concurrently,” said Eversource representative Joshua Sklodowska-Johnson of the different aspects of construction work. The project will be performed in segments.

Saw cutting will allow for the removal of pavement for excavation, he explained. After the excavation, pipe will be installed. Concrete trucks will install the duct bank. Backfill will be added to allow for driving.

“As much as possible, we will maintain a lane of travel for traffic so the street will still be in use,” said Sklodowska-Johnson. “Our goal is to make sure that the work is as minimally invasive as possible.”

Residents can sign up for email updates at bit.ly/HopkintonMilford.

2 Comments

  1. Anonymous

    Interesting …. proposed underground cable modernization project…. isn’t that what is or is suppose to be happening on our Main Street / Downtown Revitalization Project? Of course we could ‘exercise’ some sort of leverage’ on Eversource to finish downtown before this work is approved and built.

    • Anonymous

      Don’t forget that the town(Khumalo, Westerling at the time, Select Board) rakes Eversource over the coals and impedes work any chance possible. Remember when they wanted to upgrade the cables under south street about 5 years ago? The town stuck their fingers in it so many times Eversource cut the project short and didn’t fully upgrade the system. Don’t forget to Wilson street gas plant either. Eversource is going to make Hopkinton sweat it out because “what goes around, comes around”

Related Articles

Cemetery Commission decides not to apply for CPC funding

The Cemetery Commission on Monday decided not to apply for Community Preservation Act funding via the Community Preservation Committee because it has not yet spent its previous grant awards. Under the CPA, at least 10% of the funding raised must be allocated among...

Mike Whalen

Crews to repave, stripe section of Hayden Rowe Street

The Department of Public Works announced that J.H. Lynch & Sons will be out on Hayden Rowe Street starting Monday to complete road work. According to a notice sent by the DPW, crews conducted paving on Monday between 136-149 Hayden Rowe Street northbound and...

Charleswood Dirt

Main Street Corridor Project update: Work planned for drain manhole

Tasks for the Main Street Corridor are light for the next week, according to the latest update from the town. The main project listed for next week is work on a drain manhole at 63 Main Street. Crews will be completing miscellaneous work throughout the project as...

Road work sign

New I-90/I-495 ramp to open Saturday, overnight closures to continue

According to the latest update from the Massachusetts Department of Transportation, a new ramp at the Interstate 90/Interstate 495 interchange in Hopkinton is scheduled to open Saturday. A new I-90 westbound ramp to I-495 northbound is set to open Saturday morning....

MassDOT logo

Final preparations underway for Family Day

Organizer Pat O'Brien is optimistic about this Saturday's Hopkinton Family Day. "The weather's going to be nice," said O'Brien. "That's the main thing we're looking for." The Friends of Hopkinton, which organizes and runs Family Day annually, has been putting final...

Family Day fireworks
Key Storage 4.14.22