hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
8:16 pm, Wednesday, December 11, 2024
temperature icon 57°F
Humidity 97 %
Wind Gust: 13 mph

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: 3 transformers installed, utility line transfer work continues

by | Jul 27, 2024 | Featured: News, News

Main Street transformers

Crews install some of the long-awaited transformers on Main Street earlier this week.

Three of the 12 transformers needed for the completion of the Main Street Corridor Project were delivered this week and installed by Eversource on July 25 near the Town Common, the town announced Friday in its latest update on the project.

After a delay of several months, Town Manager Elaine Lazarus stated that six of the 12 transformers for the project would be delivered this week by Eversource. They are necessary to complete the underground installation of electrical wires. Supply chain issues was the reason given for the delay.

Overhead utility line work will continue on the west side of the project during the upcoming week.

Polar Vortex’s painting crew will continue its work on the traffic poles, repairing peeling paint. Scheduled hours for this work will be from 7 a.m. to 5 p.m., and hours may be adjusted based on traffic flow patterns. Locations for repairs include the intersections of Main Street and Commonwealth Avenue, Pleasant Street, Grove Street, Church Street, Wood Street and Hayden Rowe Street, as well as in front of the Fire Station.

The work schedule may change due to weather and existing conditions found while performing these tasks. This work may impact traffic and require lane and sidewalk closures, limiting access to driveways and entrances to businesses. Detours or alternating traffic will be used as necessary.

0 Comments

Related Articles

Discussions continue about narrow Main Street roadway

During Tuesday's Select Board meeting, board member Shahidul Mannan asked Town Manager Norman Khumalo for an explanation about the narrow roadway on the western portion of the Main Street Corridor Project. The town elected to widen the newly reconfigured roadway...

Main Street work

Town announces plan to widen narrow stretches of Main Street

The town announced Thursday that in response to concerns about a stretch of the recently reconfigured Main Street being too narrow to allow for emergency vehicles to pass through traffic, the road will be widened. The portion of Main Street affected runs from...

Main Street widening plan

Select Board roundup: Main Street progresses, new employees introduced

At Tuesday’s Select Board meeting, Town Manager Norman Khumalo indicated the Main Street Corridor Project continues to progress. “Substantial work has been completed,” Khumalo said. “We’re now focusing on doing the work that will help us wind down ahead of the...

Main Street construction
Key Storage 4.14.22