hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
7:18 pm, Thursday, October 15, 2026
50°F
75 %
Wind Gust: 5 mph
Clouds: 4%
Sunrise: 6:58 am
Sunset: 6:04 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Transformers set to arrive for Main Street Corridor Project after long delay

by | Jul 23, 2024 | Featured: News, News

Town Manager Elaine Lazarus announced Monday afternoon that six of the 12 transformers needed to complete the underground installation of electrical wires for the Main Street Corridor Project will be arriving this week from Eversource.

After months of delay due to supply chain issues that frustrated town officials and residents, Lazarus stated that the transformers “have been tested and are ready to be installed.”

“This is great news for the project, where the lack of transformers has caused project delays,” Lazarus explained, noting that she has been working with the town’s partners at Eversource. “We look forward to the transformer’s installation, which will enable the team to bring the project to completion.”

She added that the remaining six transformers “will be arriving within the next few weeks.”

Eversource has been working on overhead wire installation over the past few months while waiting for the transformers to become available.

Select Board chair Brian Herr, the board’s liaison for the Main Street Corridor Project, said at the last Select Board meeting on July 16 that he had conversations with Lazarus regarding the project as well as with the companies working on the project prior to the Select Board meeting..

“I’ve reached out to Eversource and had conversations with three different people trying to move this transformer thing along,” he said. “They have been very receptive and understand that I won’t stop calling until something happens.”

Herr also spoke with Joe Amorello, the owner of A. F. Amorello & Sons, the project’s construction company. The company this month began on the brickwork, sidewalk work, curb work, landscaping and underground utility connections from the property lines to several building foundations and into buildings as required.

0 Comments

Related Articles

Parks & Rec submits updated Pyne Field design for CPC funding

Acknowledging it would need to adjust the request upon further review, the Parks & Recreation Commission on Tuesday voted to submit a $3 million Community Preservation application for a new Pyne Field design. Per diem Parks & Rec Director Jon Lewitus...

Pyne Field

Arrests/Police Log, Oct. 14 edition

ARRESTS Oct. 8 6:20 p.m. Officers received a report of a hit and run on a Pendulum Pass mailbox. A vehicle was stopped, and officers conducted a field sobriety test. A 41-year-old man from Whitinsville was arrested and charged with leaving the scene of property...

Hopkinton police cruiser

EDAB seeks clarity on language around economic development plan

The Economic Development Advisory Board on Tuesday discussed the economic development plan presented at the Oct. 6 Select Board meeting, questioning whether its purpose was as a recommended report or a document to be enacted. Camille Jonlin, the Metropolitan Area...

Welcome to Hopkinton sign

Main Street hydrant test Wednesday could cause water discoloration

The Water-Sewer Department will perform a required hydrant flow test on Main Street Wednesday, according to a notice from the Water-Sewer Department. According to the notice, the flow test is scheduled to take place at 48-52 Main Street — the former site of...

Fire hydrant
Key Storage 4.14.22