hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
8:18 am, Thursday, April 23, 2026
46°F
84 %
Wind Gust: 10 mph
Clouds: 62%
Sunrise: 5:52 am
Sunset: 7:35 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: Preparation for brick installation expected to resume after Labor Day

by | Aug 30, 2024 | News

The town on Friday issued an update on the Main Street Corridor Project, noting that preparation for brick installation is anticipated to begin after the Labor Day holiday.

A.F. Amorello & Sons, the project’s construction company, is expected to return to on-site work. The company will saw cut the cement sidewalk and the asphalt bike lane in preparation for the brick installation. It also will work on excavation preparation for the wall at 1 West Main Street.

Amorello has been performing brickwork, sidewalk work, curb work, landscaping and underground utility connections from the property lines to several building foundations and into buildings as required over the past several weeks.

At the Aug. 27 Select Board meeting, Town Manager Elaine Lazarus said the company was expected to start the preparation work on Aug. 26 but had not been seen on-site that week as of the meeting.

Eversource crews have been performing the preliminary work associated with the transformers, which should be completed within a month. All 12 transformers were installed the previous week. Shifting power lines from being overhead to underground should begin in late September or early October.

Overhead utility line work will continue on the west side of the project during the upcoming week, while work on underground utility connections from property lines to building foundations also continues.

Polar Vortex’s painting crew will continue its work on the traffic poles, where paint was peeling. Scheduled hours for this work will be from 7 a.m. until 5 p.m. Locations for repairs include the intersections of Main Street and Commonwealth Avenue, Pleasant Street, Grove Street, Church Street, Wood Street and Hayden Rowe Street, as well as in front of the Fire Station.

This schedule may change due to weather and existing conditions found while performing these tasks. This work may impact traffic and require lane and sidewalk closures, limiting access to driveways and entrances to businesses. Detours and alternating traffic patterns may be used as necessary.

0 Comments

Related Articles

Arrests/Police Log, April 22 edition

ARRESTS None this week.   POLICE LOG April 14 6:35 a.m. A walk-in handed in a debit card found at Middlesex Savings Bank on Main Street. 8:41 a.m. A caller reported a vehicle sped past a school bus with its stop sign out on Hayward Street. Sgt. Matthew Santoro...

Hopkinton police cruiser

DPW to start sidewalk construction on Chestnut Street Tuesday

The Department of Public Works announced last week that contractors are scheduled to begin construction of a sidewalk on Chestnut Street starting Tuesday. Along the southern side of Chestnut Street between Wild Road and Smith Road, the DPW plans to construct a...

Main Street bike lane

HPD Chief Bennett to retire June 30, ending 35-year career

Hopkinton Police Chief Joseph Bennett announced Friday in a press release that he will retire June 30. Bennett’s retirement caps 35 years of police service, nearly all of which he spent in Hopkinton. His law enforcement journey began in 1991 when he became a...

Boston Marathon
Key Storage 4.14.22