CPC approves project recommendations for ATM warrant, including $14.8M total for Center School project

by | Nov 21, 2026 | Featured: News, News

The CPC on Thursday approved several grant requests in 7-0 votes for the upcoming fiscal year. The largest amount was the total funding for $14.8 million for the anticipated cost of the Center School reuse project.

Chair Ken Weismantel explained that the entire Center School project cost was being voted on rather than “piecemealing it” so the public would have “true transparency” about the expected amount. He stressed that the money will come from multiple sources, including CPC funds, borrowing and an anticipated contribution of at least $4 million from the Hopkinton Center for the Arts. Weismantel also noted that the project’s cost may decrease once revisions are incorporated into the design.

All projects, if approved at May’s Annual Town Meeting, will be funded with available CPC funding, explained Weismantel. The exception is the Center School project, which will require a $6 million municipal loan.

The Center School reuse project has been viewed as the key to Hopkinton’s revitalization efforts. Through a public-private partnership with the Hopkinton Center for the Arts, the Center School’s historic 1928 building will be preserved. The two rear additions are being demolished as the project’s first phase, and hazardous material will be removed. They will be replaced with a three-story structure that will house HCA, Parks & Recreation and Youth & Family Services programming. The hope is that the building will become a regional destination.

Weismantel said the CPC for FY 28 would fund a total of $10.4 million, including the $6 million municipal loan, $600,000 from the historic preservation resource fund and $3.8 million from the undesignated reserve. In addition, $400,000 of unspent funds from the $2.4 million allocation approved at May’s ATM will be diverted to this second phase of the project.

The chair described the project as a “very unique opportunity.”

Under the Community Preservation Act, municipalities can create a community preservation fund. Money can be allocated from it toward open space preservation, recreation, historic preservation and affordable housing proposals, with 10% of total CPA funding diverted to each of the four buckets. The remaining undesignated money can be used toward any of the four purposes. The money comes from a 2% real property tax surcharge approved in 2001. Total CPC money has averaged $2.1 million annually over the past several years, Weismantel said.

Funding structure explained

Weismantel explained that the CPC would borrow $6 million for this project, to be repaid over a 20-year period. All debt service payments would be made from the CPC’s undesignated funds reserve bucket.

There was a provision that no money could be spent prior to receipt of the HCA’s minimum contribution, with the exception of “not more than $3 million” for the preparation of bid documents and renovations to the building’s exterior.

“I think, coming from the Historical Commission perspective, we would still want the building to be restored,” said member Brian Colella. “And that’s a big step in getting it there.”

Weismantel added that because it would be municipal debt, interest would be paid on the balance each year. This would lower the interest payments over time.

Concerns previously were raised that the HCA would not be able to fund its contribution because it is primarily based on a federal grant funding request. Due to bureaucratic challenges, the HCA’s request has not been taken up by Congress because the body was waiting until after the recent midterm elections.

Borrowing money was seen as part of a “contingency plan” presented at the previous meeting by Permanent Building Committee chair Dan McIntyre, who has spearheaded the project.

Vice chair Eric Sonnett said the exterior building renovations will increase the Center School’s property value beyond the $3 million price tag. This prompted Open Space Preservation Commission liaison Steve Levandosky to ask if the allocation would allow for the building to be sold, in case plans fell through. Weismantel said that it could be, but a historic preservation restriction would be in place.

Weismantel added that an updated project estimate is due in February. He expects the project cost to decrease by $1.5 million, due to changes in materials and a smaller lobby.

Pickleball/tennis lighting request approved

After a brief discussion, the board voted in favor of the Parks & Recreation Commission’s request for $250,000 for lighting at the pickleball/tennis courts off Fruit Street.

Levandosky asked for more detailed information on after-hours pickleball play. He also expressed concerns about the impact of the lighting on nocturnal wildlife that were raised at the last meeting.

Parks & Rec liaison Dan Terry noted that 17 people were signed up to play pickleball at the Milford pickleball courts on the night of the meeting.

Said Terry: “So there is demand for it.”

Other requests approved

Other requests approved included:

  • $109,000 for lighting upgrades at Carrigan Park (which includes a $10,000 contribution from Hopkinton Little League);
  • $15,000 for the OSPC to have the Hughes property surveyed and staked, allowing the conservation restriction process to move forward;
  • $22,000 from the Board of Library Trustees for an engineering study to refurbish the bell and belfry at the library;
  • $15,000 from the Board of Library Trustees for the restoration of a plaque honoring Hopkinton’s Civil War veterans at the former library main entrance at 13 Main Street.

In addition, the committee voted to allow the transfer of $700,000 of an existing $1 million grant awarded for FY 24 for a cricket pitch/baseball field plan for Pyne Field to go toward Little League field upgrades. This vote also called for approximately $150,000 of this grant to be used for the design and bid package for the cricket pitch.

Three OSPC placeholders were approved for potential purchase and sale or easement agreements for land on Fruit Street, the McBride land and the Pyne Island land, respectively.

Weismantel said it was his understanding that all warrant articles needed to be submitted to Town Hall by the end of February.

Added Weismantel: “We can always entertain late [articles] for property if we find willing sellers at a later date.”

0 Comments

Submit a Comment

Your email address will not be published. Required fields are marked *

Related Articles

Select Board approves town Boston Marathon bib distribution policy

https://www.youtube.com/watch?v=VuZAkodnk18 The Select Board on Tuesday approved 4-1 the distribution of Boston Marathon invitational entries to town departments and charitable organizations. Vice chair Matthew Kizner cast the dissenting vote. Town Manager Elaine...

Town Hall

HPD files elder abuse complaint against contractor at Golden Pond

Hopkinton Police last week filed an elder abuse complaint against an independent contractor working inside Golden Pond Assisted Living after a resident needing medical assistance was left alone in her residence. According to a police report, HPD officer Augusto...

Golden Pond sign

Arrests/Police Log, Nov. 18 edition

ARRESTS Nov. 13 9:31 p.m. Units responded to West Main Street and took a 28-year-old Milford man into custody. He was charged with operating a vehicle with a suspended license, second offense operation of a vehicle under the influence of liquor, possession of an...

Hopkinton police cruiser
Key Storage 4.14.22