Main Street Corridor Project update: Sidewalk pouring planned for next week

by | Jul 30, 2026 | News

A subcontractor for A.F. Amorello & Sons will on site next week to pour concrete for sidewalks, according to the latest Main Street Corridor Project update.

In addition to the sidewalk pouring, Amorello’s casting subcontractor will be raising castings on Main Street starting Monday and continuing through Friday.

FInal paving on the east side of the project from the fire station to Ray Street currently is planned for the week of Aug. 17.

Weather and other existing conditions may change the projected work schedule. Detours or alternating traffic will be used as needed for project work. For the most up-to-date information, visit the town’s project website at hopkintonmainstreet.com.

0 Comments

Related Articles

Hydrant tests planned for South Street Saturday

Water-Sewer Manager Jed Fenneuff announced his department would be conducting hydrant flow tests at multiple locations on South Street Saturday. Fenneuff stated in a notice that the tests will take place from 7 a.m.-1 p.m. and may result in temporary water...

Fire hydrant

Select Board preps for STM Monday

https://www.youtube.com/watch?v=OSf2YER0Fh4&t=4233s The Select Board on Tuesday reviewed Monday's Special Town Meeting warrant and decided not to vote on the citizens’ petitions that comprised the bulk of its 26 articles. Chair Shahidul Mannan noted the board...

Annual Town Meeting
Key Storage 4.14.22