hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
9:12 am, Tuesday, September 22, 2026
55°F
80 %
Wind Gust: 13 mph
Clouds: 81%
Sunrise: 6:33 am
Sunset: 6:44 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: Wall, walkway work continue

by | Oct 18, 2024 | News

The town’s latest Main Street Corridor Project update released Friday shared that wall and walkway work will resume at 35 Main Street on Monday and Tuesday.

Similar walkway work will commence at 77 Main Street on Tuesday and Wednesday . Miscellaneous work will be performed along the corridor.

Overhead utility line transfer work will continue on the west side of the project during the upcoming week. On the east side of the project, brick strip installation will resume.

Eversource crews will continue performing the preliminary work associated with the transformers. All 12 transformers have been installed. The town is awaiting information on the schedule from Eversource to begin shifting power lines from overhead to underground. This work previously was expected to begin in early October.

This schedule may change due to weather and existing conditions found while performing these tasks. This work may impact traffic and require lane and sidewalk closures, limiting access to driveways and entrances to businesses. Detours and alternating traffic patterns may be used as necessary.

0 Comments

Related Articles

Crews to repave, stripe section of Hayden Rowe Street

The Department of Public Works announced that J.H. Lynch & Sons will be out on Hayden Rowe Street starting Monday to complete road work. According to a notice sent by the DPW, crews conducted paving on Monday between 136-149 Hayden Rowe Street northbound and...

Charleswood Dirt

Main Street Corridor Project update: Work planned for drain manhole

Tasks for the Main Street Corridor are light for the next week, according to the latest update from the town. The main project listed for next week is work on a drain manhole at 63 Main Street. Crews will be completing miscellaneous work throughout the project as...

Road work sign

New I-90/I-495 ramp to open Saturday, overnight closures to continue

According to the latest update from the Massachusetts Department of Transportation, a new ramp at the Interstate 90/Interstate 495 interchange in Hopkinton is scheduled to open Saturday. A new I-90 westbound ramp to I-495 northbound is set to open Saturday morning....

MassDOT logo

Final preparations underway for Family Day

Organizer Pat O'Brien is optimistic about this Saturday's Hopkinton Family Day. "The weather's going to be nice," said O'Brien. "That's the main thing we're looking for." The Friends of Hopkinton, which organizes and runs Family Day annually, has been putting final...

Family Day fireworks
Key Storage 4.14.22