hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
2:55 pm, Sunday, November 24, 2024
temperature icon 45°F
Humidity 48 %
Wind Gust: 16 mph

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: Eastbound detours resume this week

by | Oct 30, 2022 | News

As part of the Main Street Corridor Project this week, the eastbound detour from Grove Street to Maple Street to Hayden Rowe Street and back to Main Street will be in place from Monday through Friday. Additionally, the eastbound detour from Pleasant Street to Maple Street to Hayden Rowe Street and back to Main Street will be used as needed.

On the east side of the project, workers will continue the service connections from Muffin House toward Ash Street.

On the west side of the project, the contractor will focus on curb work between Wood Street and the Fire Station beginning Tuesday or Wednesday.

Working hours for the Main Street Corridor Project are 7 a.m. until 3 p.m. No detours, one-lane closures or road closures are allowed from 7-9 a.m.

This schedule may change due to weather and existing conditions found while performing the planned tasks. For the most up-to-date information, visit the town’s project website at hopkintonmainstreet.com.

0 Comments

Related Articles

Main Street Corridor Project update: Walkway work continues

The town’s latest Main Street Corridor Project update released Friday shared that walkway work will resume on Main Street during the upcoming week. Addresses affected by this work include 35, 36 and 77 Main Street. Miscellaneous work also will continued along the...

Main Street brickwork
Key Storage 4.14.22