hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
3:20 pm, Tuesday, September 22, 2026
63°F
56 %
Wind Gust: 13 mph
Clouds: 65%
Sunrise: 6:33 am
Sunset: 6:44 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: Eastbound detour at Pleasant Street in place all week

by | Dec 4, 2022 | News

As part of the Main Street Corridor Project this week, the eastbound detour from Pleasant Street to Maple Street to Hayden Rowe Street and back to Main Street will be in place Monday through Friday. The eastbound detour from Grove Street to Maple Street to Hayden Rowe Street and back to Main Street will be used on an as-needed basis.

On the west side of the project, between Wood Street and the Fire Station, the contractor will continue winterizing — paving any unfinished driveways and continue placing brick/granite walkways.

On the east side of the project, workers will continue underground service connections between Muffin House Cafe and Church Street.

Project-wide, the contractor will perform electric manhole work.

Working hours for the Main Street Corridor Project are 7 a.m. until 3 p.m. No detours, one-lane closures or road closures are allowed from 7-9 a.m.

This schedule may change due to weather and existing conditions found while performing the planned tasks. For the most up-to-date information, visit the town’s project website at hopkintonmainstreet.com.

0 Comments

Related Articles

Cemetery Commission decides not to apply for CPC funding

The Cemetery Commission on Monday decided not to apply for Community Preservation Act funding via the Community Preservation Committee because it has not yet spent its previous grant awards. Under the CPA, at least 10% of the funding raised must be allocated among...

Mike Whalen

Crews to repave, stripe section of Hayden Rowe Street

The Department of Public Works announced that J.H. Lynch & Sons will be out on Hayden Rowe Street starting Monday to complete road work. According to a notice sent by the DPW, crews conducted paving on Monday between 136-149 Hayden Rowe Street northbound and...

Charleswood Dirt

Main Street Corridor Project update: Work planned for drain manhole

Tasks for the Main Street Corridor are light for the next week, according to the latest update from the town. The main project listed for next week is work on a drain manhole at 63 Main Street. Crews will be completing miscellaneous work throughout the project as...

Road work sign

New I-90/I-495 ramp to open Saturday, overnight closures to continue

According to the latest update from the Massachusetts Department of Transportation, a new ramp at the Interstate 90/Interstate 495 interchange in Hopkinton is scheduled to open Saturday. A new I-90 westbound ramp to I-495 northbound is set to open Saturday morning....

MassDOT logo

Final preparations underway for Family Day

Organizer Pat O'Brien is optimistic about this Saturday's Hopkinton Family Day. "The weather's going to be nice," said O'Brien. "That's the main thing we're looking for." The Friends of Hopkinton, which organizes and runs Family Day annually, has been putting final...

Family Day fireworks
Key Storage 4.14.22