The Conservation Commission on Tuesday asked the Deerfield Estates homeowners association to discuss remedies for incomplete dry well installation that has prevented the development from receiving a certificate of compliance more than two decades after its construction.
The commission voted 5-0 to continue the hearing until its next meeting on Dec. 15 so that an HOA representative could attend and provide feedback.
It previously issued an order of conditions for Deerfield Estates, a 55-plus condominium complex located at 148 Lumber Street, in 2003, according to conservation administrator Judy Day.
“The applicant had initially applied for their COC back in 2010,” Day explained. “Discussions [were] continuing all the way through 2023, but the COC was ultimately not issued due to a lack of information.”
The project was out of compliance with one condition, she noted. Roof runoff was supposed to be tied into dry wells or the stormwater management system.
The applicant, Capital Group Properties, came before the commission with a revised as-built plan. Day said “ground-penetrating radar” was used to locate subsurface stormwater management capabilities.
In addition to noncompliance regarding the roof runoff, Day explained that Pare Corporation, the peer review consultant, also found that the development was noncompliant with the groundwater recharge condition.
Pare representative Bobby Sykes said the initial review in 2023 and current documents provided by the applicant showed that only 10 of 18 units “appear to be tied in” to the system.
Added Sykes: “It appears from the conditions that recharge was critical in this area due to the presence of wetlands and adjacent vernal pools as well.”
Justin Depietri from Capital Group Properties said he became involved with this project around 2023.
“I know it’s not in compliance 100%,” he said. “But the place has been established for, you know, over 20 years.”
Depietri noted that the engineering company originally working on this project apparently is out of business. This has prevented him from obtaining records.
“Usually there’s a pretty good reason and concern for the commission to put in a condition like that,” said chair Melissa Recos. “[T]o close this out, you really would need to meet the conditions of the permit.”
Depietri said that would involve digging up people’s yards.
Asked Recos: “So, can we do that?”
“Not easily,” said Depietri after a long pause. “And not without pissing off a lot of people.”
He added that his company no longer manages the development, adding another complication.
Members requested that representatives from the homeowners association come to the next meeting. Day said she would work with Depietri to facilitate a discussion.
West Main tree replanting OK’d
In a 4-1 vote, the commission approved a new timeline for the replanting of trees to replace a damaged white pine on a problematic home construction site off West Main Street near Elm Street. Member Ed Harrow was the lone dissenter.
The project has been cited with multiple past violations because the contractor removed six trees without permission. Erosion controls were damaged, and bark was stripped from trees. Eleven trees were severely damaged, and vegetation was dumped outside the limit of work.
At that time, co-vice chair Ted Barker-Hook called this situation the “most egregious violation I have seen in my time on the commission.”
On Nov. 3, an enforcement order was issued for the removal of the white pine tree with a 22-inch caliper. Damage made it unlikely to survive, according to an arborist’s report. It might also fall on the new home, according to engineer Sam Malafronte.
Malafronte pointed out that the enforcement order required two trees to be planted in its place within six months. The applicant, Yuan Li, requested via Malafronte that it be incorporated in the site planting plan instead. This would occur after the home is built.
Including the white pine removal in the plan would ensure that a landscaping company would be on-site to manage the entire planting process, according to Malafronte. Forty-eight other trees will be planted, he said, and the white pine is “still standing.”
Recos said she would prefer that it be done within six months, per the enforcement order. But she ultimately voted in favor of incorporating this tree into the overall plan.
Day pointed out that although the time frame has been altered, the enforcement order is still in effect.
Braim bridge exemption approved
The commission voted 4-0 to approve an exemption request for the Hopkinton Area Land Trust (HALT) to construct a trail bridge at the Braim Farm conservation area off South Mill Street.
HALT director Chuck Dauchy proposed a plan to construct a trail bridge that would provide “year-round trail access.” It would be built over an overflow channel of a perennial stream and have a 23-foot span.
He added that it “is set up to completely bridge the 100-year floodplain.”
While a culvert there carries stream flow for most of the year, the trail becomes “unpassable” during wet periods, he pointed out.
Dauchy said he hoped the commission would issue a project exemption, as it has done for similar projects.
Recos, who had attended a recent site walk, said the situation was different because of the presence of a riverfront. She initially thought that a request for determination of applicability (RDA) would be more appropriate because it would allow the Massachusetts Department of Environmental Protection to review the request. She reconsidered when Day said she could draft an exemption letter, potentially with conditions.
Harrow, who also attended the site walk, said he was “all in favor” of the project. It will use material from the iconic billboards that previously were removed from property overseen by the Open Space Preservation Commission, which he chairs. Harrow acquired three catwalks from the billboards, which were taken down during construction of the Elmwood Farms development off Blueberry Lane.
Member Walter Garland asked that the least expensive option for HALT, a nonprofit, be approved.
“I think what they’re trying to do is going to be perfect for this spot,” said Garland.
Recos pointed out that Dauchy needs to get permission from the abutter to access their property to begin the work. Harrow offered to speak with the abutter.
Hearings continued
Two hearings were continued until Dec. 15. They were in regard to the proposed improvements to the Sandy Beach parking lot at 4 Lakeshore Drive and the Department of Public Works request for a culvert replacement off Granite Street. A certificate of compliance request for the parking lot also will be considered at this meeting.
Additionally, members voted 5-0 to continue the discussion of proposed wetlands regulation changes to Jan. 12. This will be the third dedicated meeting on the topic.