The Department of Public Works announced it will continue roadwork through the end of this month and into the beginning of August.
Work hours are approximately 7 a.m.-5 p.m., during which residents are asked not to park along the sides of the affected streets. Residents also should expect delays.
The work schedule is as follows:
July 23-24
Paving binder course on Tiffany Trail, Lyn Path and Erika Drive.
Adjusting structures and ADA ramps on Valleywood Road, Circle Drive, Tiffany Trail, Lyn Path and Erika Drive.
July 27
Installing berms in cul de sacs on Valleywood Road, Circle Drive and Lyn Path. A berm at the entrance to Erika Drive also will be completed.
Aug. 3
Paving top course on Valleywood Road and Circle Drive.
Aug. 4
Paving top course on Tiffany Trail, Lyn Path and Erika Drive.