hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
12:39 pm, Monday, September 21, 2026
64°F
68 %
Wind Gust: 20 mph
Clouds: 31%
Sunrise: 6:32 am
Sunset: 6:46 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Crews to repave, stripe section of Hayden Rowe Street

by | Sep 21, 2026 | Featured: News, News

The Department of Public Works announced that J.H. Lynch & Sons will be out on Hayden Rowe Street starting Monday to complete road work.

According to a notice sent by the DPW, crews conducted paving on Monday between 136-149 Hayden Rowe Street northbound and southbound. Paving work was scheduled between 7 a.m.-3 p.m. Access to and from driveways in this area was limited, and residents needing access to their vehicles were advised to park on Chamberlain Street. Eastbound traffic on Chamberlain was detoured via Angelo Drive, Colella Farm Road, Nicholas Road and Teresa Road back to Hayden Rowe Street for the duration of paving.

Crews will be back in the area Wednesday and Thursday from 9 a.m.-2 p.m. for temporary striping. Temporary lane closures throughout the day are anticipated.

The DPW notice also informed residents that guardrail installation is planned for next week and may include fence work at 137 and 149 Hayden Rowe Street.

An asphalt curb adjacent to the northbound drive lane is temporary, according to the notice. It reportedly is intended to accommodate paving due to the utilities “not completing their line relocations and pole removals before the start of school as intended,” the notice states. Temporary curb cuts are set to be removed for the completion of paving and striping next spring.

The paving work on Hayden Rowe Street was deemed necessary after utility delays prevented the removal of existing poles that obstruct the final roadway and prohibit its completion. The work, which is associated with the Charleswood School project, was discussed at an Elementary School Building Committee meeting on Sept. 16. It will restore the existing plowable road surface and give the utility companies additional time to complete their work.

0 Comments

Submit a Comment

Your email address will not be published. Required fields are marked *

Related Articles

Main Street Corridor Project update: Work planned for drain manhole

Tasks for the Main Street Corridor are light for the next week, according to the latest update from the town. The main project listed for next week is work on a drain manhole at 63 Main Street. Crews will be completing miscellaneous work throughout the project as...

Road work sign

New I-90/I-495 ramp to open Saturday, overnight closures to continue

According to the latest update from the Massachusetts Department of Transportation, a new ramp at the Interstate 90/Interstate 495 interchange in Hopkinton is scheduled to open Saturday. A new I-90 westbound ramp to I-495 northbound is set to open Saturday morning....

MassDOT logo

Arrests/Police Log, Sept. 16 edition

ARRESTS Sept. 10 8:16 p.m. Units responded to South Street following a call about a person throwing glass out of a vehicle. Officers stopped a vehicle and took a 29-year-old man from Hopedale and a 34-year-old woman from Milford into custody. The male was charged...

Hopkinton police cruiser
Key Storage 4.14.22