The Department of Public Works has scheduled roadwork through the month of July that is slated to begin on Thursday.
Work hours are approximately 7 a.m.-5 p.m., during which residents are asked not to park along the sides of the affected streets.
The work schedule for July is as follows:
July 9
Lowering manholes on Erika Drive, Valleywood Road, Circle Drive and Lyn Path.
July 13-15
Reclaiming and grading of Valleywood Road and Circle Drive.
July 16-17
Paving binder course on Valleywood Road and Circle Drive.
July 20-22
Reclaiming and grading of Tiffany Trail, Lyn Path and Erika Drive.
Sidewalk excavation on Erika Drive from Pond Street to Lyn Path.
July 22-24
Raising and adjusting structures on Valleywood Road, Circle Drive, Tiffany Trail, Lyn Path & Erika Drive.
July 23-24
Paving binder course on Tiffany Trail, Lyn Path and Erika Drive.
July 27
Installing asphalt berms in cul de sacs on Valleywood Road, Circle Drive and Lyn Path.
Sidewalk paving on Erika Drive from Pond Street to Lyn Path.