hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
3:27 pm, Saturday, November 2, 2024
temperature icon 52°F
Humidity 61 %
Wind Gust: 6 mph

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: Construction meeting held; transformers still not available

by | Jan 26, 2024 | Business, News

The town issued a press release Friday with updates about the Main Street Corridor Project following a construction meeting that was held Tuesday.

At the meeting were representatives from the town, engineering consultant VHB, the Massachusetts Department of Transportation (MassDOT), project contractor Amorello and Eversource.

Amorello has not set a time for returning to the project, according to the press release. Utility work, including both overhead and underground work, needs to be completed before Amorello will be able to schedule any work.

Eversource continues to await the transformers, stating that there is no new information available. The utility company anticipates starting the transfer of overhead electrical lines to the new utility poles in about a month, although no definitive date has been set. MassDOT confirmed that a utility meeting will be held once a date is confirmed.

When the transfer of overhead utilities is complete, the old poles will be removed. This will allow work to be completed from Wood Street to the Fire Station, where the utilities are not being undergrounded.

Amorello will not be able to continue work from the Fire Station to Ash Street until Eversource is able to complete the underground portion of the project in this area.

Regarding complaints about peeling paint on the new signal poles, MassDOT is reviewing another repair-in-place process from the manufacturer to determine if the process is acceptable. It will need to be field tested before final approval. The town noted that replacement is preferred.

Weekly construction advisories will resume when there are weekly updates on the project. Until then, the town will send project updates as needed.

0 Comments

Related Articles

Main Street Corridor Project update: Winter shutdown arrives

The town announced that the Main Street Corridor Project is in winter shutdown. The contractor, A.F. Amorello & Sons, is off-site until spring 2024, barring any emergencies or repairs. Winterization of the project is substantially complete. The Massachusetts...

Road work sign

Main Street Corridor Project update: Sign work possible this week

As part of the Main Street Corridor Project this week, Road Safe may be on-site for sign work — resetting, removing and replacing. Working hours for the Main Street Corridor Project are 7 a.m. until 3 p.m. No detours, one-lane closures or road closures are allowed...

Road work sign

Main Street Corridor Project update: Cleanup, sign work this week

As part of the Main Street Corridor Project this week, crews will focus on site cleanup and "punch list" work. Road Safe is scheduled to be on-site for signs (resetting, removing and replacing). Work is scheduled for Saturday (Oct. 21), and police details will be...

Road work sign
Key Storage 4.14.22