hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
9:15 am, Tuesday, September 22, 2026
55°F
80 %
Wind Gust: 13 mph
Clouds: 81%
Sunrise: 6:33 am
Sunset: 6:44 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: Eastbound detour via Grove Street this week

by | Oct 9, 2022 | News

As part of the Main Street Corridor Project this week, an eastbound detour from Grove Street to Maple Street to Hayden Rowe Street and back to Main Street will be in place for work in the area of the Route 135/Route 85 intersection.

Work will include the installation of street lighting foundations and conduit along with new traffic signals, grading of sidewalk areas on Grove Street and Cedar Street, completion of pavement on Grove Street (if Eversource’s work is complete), and, potentially, the installation of curbing on Cedar Street and Grove Street.

On the west side of the project, workers will continue fine grading and compacting sidewalks from Wood Street toward the Fire Station, complete driveways on West Main Street (depending on scheduling), perform concrete sidewalk work at the end of driveways (affected property owners will be notified in advance), and perform asphalt work at the end of driveways for properties that have an asphalt driveway apron (homeowners will be notified, and westbound traffic on Main Street will be detoured to Wood Street as needed).

Working hours for the Main Street Corridor Project are 7 a.m. until 3 p.m. No detours, one-lane closures or road closures are allowed from 7-9 a.m.

This schedule may change due to weather and existing conditions found while performing the planned tasks. For the most up-to-date information, visit the town’s project website at hopkintonmainstreet.com.

0 Comments

Related Articles

Crews to repave, stripe section of Hayden Rowe Street

The Department of Public Works announced that J.H. Lynch & Sons will be out on Hayden Rowe Street starting Monday to complete road work. According to a notice sent by the DPW, crews conducted paving on Monday between 136-149 Hayden Rowe Street northbound and...

Charleswood Dirt

Main Street Corridor Project update: Work planned for drain manhole

Tasks for the Main Street Corridor are light for the next week, according to the latest update from the town. The main project listed for next week is work on a drain manhole at 63 Main Street. Crews will be completing miscellaneous work throughout the project as...

Road work sign

New I-90/I-495 ramp to open Saturday, overnight closures to continue

According to the latest update from the Massachusetts Department of Transportation, a new ramp at the Interstate 90/Interstate 495 interchange in Hopkinton is scheduled to open Saturday. A new I-90 westbound ramp to I-495 northbound is set to open Saturday morning....

MassDOT logo

Final preparations underway for Family Day

Organizer Pat O'Brien is optimistic about this Saturday's Hopkinton Family Day. "The weather's going to be nice," said O'Brien. "That's the main thing we're looking for." The Friends of Hopkinton, which organizes and runs Family Day annually, has been putting final...

Family Day fireworks
Key Storage 4.14.22