hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
11:31 pm, Friday, November 22, 2024
temperature icon 40°F
Humidity 95 %
Wind Gust: 8 mph

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: Multiple eastbound detours in place

by | Oct 23, 2022 | News

As part of the Main Street Corridor Project this week, the eastbound detour from Grove Street to Maple Street to Hayden Rowe Street and back to Main Street will be in place from Monday through Friday. Additionally, the eastbound detour from Pleasant Street to Maple Street to Hayden Rowe Street and back to Main Street will be used on Tuesday.

On the east side of the project, the contractor will continue work on underground service connections up to property lines from Church Street to the Route 135/Route 85 intersection.

At the 135/85 intersection, work will continue on the new traffic signal.

Project-wide, the contractor will raise castings on manholes and work on temporary paving for driveways and back of sidewalk gravel areas.

Working hours for the Main Street Corridor Project are 7 a.m. until 3 p.m. No detours, one-lane closures or road closures are allowed from 7-9 a.m.

This schedule may change due to weather and existing conditions found while performing the planned tasks. For the most up-to-date information, visit the town’s project website at hopkintonmainstreet.com.

0 Comments

Related Articles

Main Street Corridor Project update: Walkway work continues

The town’s latest Main Street Corridor Project update released Friday shared that walkway work will resume on Main Street during the upcoming week. Addresses affected by this work include 35, 36 and 77 Main Street. Miscellaneous work also will continued along the...

Main Street brickwork
Key Storage 4.14.22