Main Street Corridor Project update: Multiple eastbound detours in place

by | Oct 23, 2022 | News

As part of the Main Street Corridor Project this week, the eastbound detour from Grove Street to Maple Street to Hayden Rowe Street and back to Main Street will be in place from Monday through Friday. Additionally, the eastbound detour from Pleasant Street to Maple Street to Hayden Rowe Street and back to Main Street will be used on Tuesday.

On the east side of the project, the contractor will continue work on underground service connections up to property lines from Church Street to the Route 135/Route 85 intersection.

At the 135/85 intersection, work will continue on the new traffic signal.

Project-wide, the contractor will raise castings on manholes and work on temporary paving for driveways and back of sidewalk gravel areas.

Working hours for the Main Street Corridor Project are 7 a.m. until 3 p.m. No detours, one-lane closures or road closures are allowed from 7-9 a.m.

This schedule may change due to weather and existing conditions found while performing the planned tasks. For the most up-to-date information, visit the town’s project website at hopkintonmainstreet.com.

0 Comments

Related Articles

Arrests/Police Log, May 6 edition

ARRESTS None this week.   POLICE LOG April 28 12:10 a.m. A caller called numerous times to talk about her aunt. She did not want police to respond, and she was advised that eviction is a civil process. 12:24 a.m. Officer Aline Matos checked on a vehicle parked...

Hopkinton police cruiser
Key Storage 4.14.22