hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
11:05 pm, Saturday, December 21, 2024
temperature icon 15°F
Humidity 70 %
Wind Gust: 14 mph

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: Painting repairs completed on mast arms throughout project

by | Sep 8, 2024 | News

The town’s latest Main Street Corridor Project update notes that Polar Vortex has completed painting the mast arms, the structures on which traffic lights are mounted, throughout the project.

Polar Vortex’s crew has been painting the traffic poles, where paint was peeling, for the past several weeks. Locations included the intersections of Main Street and Commonwealth Avenue, Pleasant Street, Grove Street, Church Street, Wood Street and Hayden Rowe Street, as well as in front of the Fire Station. The company may return for final touch-ups at a future date.

A.F. Amorello & Sons, the project’s construction company, is expected to return to on-site work this week. It will be prepping the brick strip along the bike lane and continuing its wall work at 1 West Main Street.

Overhead utility line transfer work will continue on the west side of the project during the upcoming week.

Eversource crews have been performing the preliminary work associated with the transformers, which should be completed within the next month. All 12 transformers have been installed. Shifting power lines from being overhead to underground should begin in late September or early October.

This schedule may change due to weather and existing conditions found while performing these tasks. This work may impact traffic and require lane and sidewalk closures, limiting access to driveways and entrances to businesses. Detours and alternating traffic patterns may be used as necessary.

0 Comments

Related Articles

Main Street Corridor Project update: Utility work continues

The town’s latest Main Street Corridor Project update released Friday shared that utility companies will be on-site for work during the coming week. Dagle Electric will continue service cut-overs on the east side of the project. Affected abutters will be notified...

Road work sign

Main Street Corridor Project update: Utility work continues

The town’s latest Main Street Corridor Project update released Friday shared that utility companies will be on-site for work during the coming week. Dagle Electric will continue service cut-overs on the east side of the project. Affected abutters will be notified...

Road work sign

Main Street Corridor Project update: Utility work continues

The town’s latest Main Street Corridor Project update released Friday shared that utility work will continue over the next two weeks, with the exception of Nov. 28-29 in observance of the Thanksgiving holiday. Eversource will be on-site to work on underground...

Road work sign
Key Storage 4.14.22