hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
3:20 am, Wednesday, September 23, 2026
46°F
90 %
Wind Gust: 6 mph
Clouds: 99%
Sunrise: 6:34 am
Sunset: 6:42 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: Paving delayed to next week due to weather

by | Nov 10, 2025 | Featured: News, News

In a construction advisory released Monday, the town notified residents that paving as part of the Main Street Corridor Project has been delayed until next week.

A.F. Amorello & Sons initially scheduled tentative dates for final paving of the west side of the project for Wednesday and Thursday this week. Because of weather, the timeline has been extended, with work potentially to begin next Monday.

Paving limits extend from the Fire Station to just past the Wood Street intersection. Work may impact traffic and require lane and sidewalk closures along with potential detours. Per town policy, lane closures are limited to 9 a.m.-3 p.m.

Alternating traffic will be used downtown between 9 a.m.-3 p.m. Delays are expected and detours will be needed.

No work is scheduled for Tuesday in observance of the Veterans Day holiday.

Weather and other existing conditions may change the projected work schedule. For the most up-to-date information, visit the town’s project website at hopkintonmainstreet.com.

0 Comments

Related Articles

Cemetery Commission decides not to apply for CPC funding

The Cemetery Commission on Monday decided not to apply for Community Preservation Act funding via the Community Preservation Committee because it has not yet spent its previous grant awards. Under the CPA, at least 10% of the funding raised must be allocated among...

Mike Whalen

Crews to repave, stripe section of Hayden Rowe Street

The Department of Public Works announced that J.H. Lynch & Sons will be out on Hayden Rowe Street starting Monday to complete road work. According to a notice sent by the DPW, crews conducted paving on Monday between 136-149 Hayden Rowe Street northbound and...

Charleswood Dirt

Main Street Corridor Project update: Work planned for drain manhole

Tasks for the Main Street Corridor are light for the next week, according to the latest update from the town. The main project listed for next week is work on a drain manhole at 63 Main Street. Crews will be completing miscellaneous work throughout the project as...

Road work sign

New I-90/I-495 ramp to open Saturday, overnight closures to continue

According to the latest update from the Massachusetts Department of Transportation, a new ramp at the Interstate 90/Interstate 495 interchange in Hopkinton is scheduled to open Saturday. A new I-90 westbound ramp to I-495 northbound is set to open Saturday morning....

MassDOT logo

Final preparations underway for Family Day

Organizer Pat O'Brien is optimistic about this Saturday's Hopkinton Family Day. "The weather's going to be nice," said O'Brien. "That's the main thing we're looking for." The Friends of Hopkinton, which organizes and runs Family Day annually, has been putting final...

Family Day fireworks
Key Storage 4.14.22