hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
4:15 am, Friday, December 5, 2025
10°F
54 %
Wind Gust: 6 mph
Clouds: 0%
Sunrise: 6:59 am
Sunset: 4:14 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: Sidewalk work continues, detours possible

by | Sep 4, 2022 | News

Main Street construction

With the Route 135/Route 85 intersection paved and lined last week, workers this week will focus on rebuilding the sidewalks. PHOTO/JERRY SPAR

Work on the Main Street Corridor Project continues this week — although there will be no work Monday due to the Labor Day holiday — with the focus being to continue the service connections project wide and continue sidewalk installation on the project’s west side, the town announced. Pleasant Street and Elm Street detours will be used as needed.

New granite curbs will be installed along Main Street working eastbound from West Main Street to the Fire Station. Workers will continue to grade and compact and continue forming sidewalks between Wood Street and the Fire Station. Affected property owners will be notified in advance when concrete sidewalk work will take place at the end of driveways, as access will be impacted (emergency vehicle access will be maintained).

On East Main Street, workers will continue Comcast duct bank work.

This schedule may change due to weather and existing conditions found while performing the planned tasks. For the most up-to-date information, visit the town’s project website at hopkintonmainstreet.com.

0 Comments

Related Articles

Main Street Corridor Project update: Amorello to begin paving Monday

The latest update for the Main Street Corridor Project released Friday details plans for A.F. Amorello & Sons to begin paving next week. Amorello is scheduled to pave the west side of the project Monday and Tuesday. The Hopkinton Police Department has approved...

Road work sign

Main Street Corridor Project update: Paving, curb work delayed

According to the latest update for the Main Street Corridor Project, paving has been delayed due to weather and subcontractor schedules. A.F. Amorello & Sons previously provided the town with tentative plans to begin paving work Nov. 5-6. New dates have not...

Main Street pole
Key Storage 4.14.22