hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
12:43 pm, Tuesday, December 3, 2024
temperature icon 34°F
Humidity 58 %
Wind Gust: 8 mph

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: Sidewalk work this week; peeling light poles eventually will be replaced

by | Sep 17, 2023 | Business, News

As part of the Main Street Corridor Project this week, crews will form and pour sidewalks, and place loam and seeding in various areas.

Sidewalks are nearing completion, but changes are required in the area in front of the Korean Presbyterian Church (2 Main Street). The area in front of the church should have loam and seed to accommodate trees. The concrete that was poured will need to be removed.

Regarding the peeling light poles, the Massachusetts Department of Transportation (MassDOT), which is overseeing the project, indicated the poles will be replaced but did not give a timeline.

At the Aug. 22 construction meeting, Eversource confirmed there is no update on transformer availability, which is delaying completion of the utility work. As such, the final course of pavement likely will not be completed this year.

Most traffic and speed limit signs have been placed. The town has requested that MassDOT remove the second pole from street signs. Street signs will be mounted on single poles. MassDOT will be scheduling work for the remaining poles.

Working hours for the Main Street Corridor Project are 7 a.m. until 3 p.m. No detours, one-lane closures or road closures are allowed from 7-9 a.m.

This schedule may change due to weather and existing conditions found while performing the planned tasks. For the most up-to-date information, visit the town’s project website at hopkintonmainstreet.com.

0 Comments

Related Articles

Main Street Corridor Project update: Winter shutdown arrives

The town announced that the Main Street Corridor Project is in winter shutdown. The contractor, A.F. Amorello & Sons, is off-site until spring 2024, barring any emergencies or repairs. Winterization of the project is substantially complete. The Massachusetts...

Road work sign

Main Street Corridor Project update: Sign work possible this week

As part of the Main Street Corridor Project this week, Road Safe may be on-site for sign work — resetting, removing and replacing. Working hours for the Main Street Corridor Project are 7 a.m. until 3 p.m. No detours, one-lane closures or road closures are allowed...

Road work sign
Key Storage 4.14.22