hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
3:40 am, Thursday, December 19, 2024
temperature icon 37°F
Humidity 96 %
Wind Gust: 3 mph

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: Utility line transfer work continues on project’s west side

by | Jul 19, 2024 | News

The town on Friday issued an update on the Main Street Corridor Project.

Overhead utility line work will continue on the west side of the project during the upcoming week.

Polar Vortex’s painting crew will continue its work on the traffic poles, repairing peeling paint. Scheduled hours for this work will be from 7 a.m. to 5 p.m., and hours may be adjusted based on traffic flow patterns. Locations for repairs include the intersections of Main Street and Commonwealth Avenue, Pleasant Street, Grove Street, Church Street and Hayden Rowe Street, as well as in front of the Fire Station.

A.F. Amorello will be on-site during the week of July 22 to begin work on the south side of the project. Work may include brickwork, sidewalk work, curb work and underground utility connections from the property lines to building foundations and into buildings as required.

Eversource continues to wait for transformers needed to complete the undergrounding of utilities. Supply chain challenges obtaining the transformers remains the reason for the delay.

This schedule may change due to weather and existing conditions found while performing these tasks. This work may impact traffic and require lane and sidewalk closures, limiting access to driveways and entrances to businesses. Detours or alternating traffic will be used as necessary.

0 Comments

Related Articles

Main Street Corridor Project update: Utility work continues

The town’s latest Main Street Corridor Project update released Friday shared that utility companies will be on-site for work during the coming week. Dagle Electric will continue service cut-overs on the east side of the project. Affected abutters will be notified...

Road work sign

Main Street Corridor Project update: Utility work continues

The town’s latest Main Street Corridor Project update released Friday shared that utility companies will be on-site for work during the coming week. Dagle Electric will continue service cut-overs on the east side of the project. Affected abutters will be notified...

Road work sign

Main Street Corridor Project update: Utility work continues

The town’s latest Main Street Corridor Project update released Friday shared that utility work will continue over the next two weeks, with the exception of Nov. 28-29 in observance of the Thanksgiving holiday. Eversource will be on-site to work on underground...

Road work sign

Main Street Corridor Project update: Wall, walkway work continue

The town’s latest Main Street Corridor Project update released Friday shared that wall and walkway work will resume at 35 Main Street on Monday and Tuesday. Similar walkway work will commence at 77 Main Street on Tuesday and Wednesday . Miscellaneous work will be...

Main Street brickwork
Key Storage 4.14.22