Roadwork on multiple streets in town set for July

by | Jun 27, 2025 | News

The Department of Public Works announced that construction on multiple streets in town begins next week.

Affected roads are: Chamberlain Street, Angelo Drive, Colella Farm Road, Nicholas Road and Whalen Road.

Structures will be lowered July 1-2 on Chamberlain Street, Angelo Drive, Colella Farm Road and Nicholas Road. Following this work, crews will stagger construction throughout the month.

Starting July 7, crews will start the process of reclaiming and grading the roads. The dates for that work are as follows:

July 7-10, Chamberlain Street
July 14-17, Angelo Drive and Colella Farm Road
July 21-24, Nicholas Road
July 28-31, Whalen Road

Following the grading work, crews will move on to workers excavating and installing asphalt binder course. The DPW has scheduled the following dates for completing this part of the road maintenance project:

July 11, Chamberlain Street
July 18, Angelo Drive and Colella Farm Road
July 25, Nicholas Road

On July 21, workers will adjust structures on Chamberlain Street, Angelo Drive, and Colella Farm Road.

Finally, the DPW will be installing ADA sidewalk ramps July 28-31 on Colella Farm Road and Nicholas Road.

Work hours will be approximately 7 a.m.-5 p.m. Dates are subject to change due to weather conditions. Residents are advised not to park in the affected streets, as doing so will interfere with project timelines.

Drivers should expect delays and seek alternate routes when possible.

0 Comments

Related Articles

Man struck on Wood Street dies from injuries

A Hopkinton man who was struck by a car on Wood Street in October has died from his injuries, according to his obituary published Wednesday. Jay Clifford Boggis, 79, was walking with his dog on the evening of Oct. 11 in the area of 280 Wood Street when both were...

Hopkinton police cruiser

DPW leaders describe department constraints to WSAB

The Water and Sewer Advisory Board on Nov. 18 heard from senior staff at the Department of Public Works on the challenges it faces while providing Hopkinton with water and sewer services. DPW Director Kerry Reed and Water & Sewer Manager Jed Fenneuff told the...

PFAS filtration system at Well #6

I-90/I-495 interchange ramp to close overnight Sunday, Monday

Ramp closures at the Interstate 90/Interstate 495 interchange in Hopkinton will take place early this week, according to an update from the Massachusetts Department of Transportation. Overnight on Sunday and Monday, MassDOT plans to close the I-495 northbound ramp...

MassDOT logo
Key Storage 4.14.22