https://www.youtube.com/watch?v=vHxJE4dl7R0&t=3174s&ab_channel=HCAM The Conservation Commission at its Feb. 6 meeting questioned why an area of resource delineation request by Wall Street Development for 12 North Mill Street did not document the...
Massachusetts Laborers Training Center
Conservation Commission blasts The Trails for repeated stormwater violations
During its nearly four-hour meeting Tuesday night, the Conservation Commission lost its patience with the developer of The Trails after the project incurred additional stormwater management violations after the deluge of rain earlier in the day. The Trails, an 80-unit...
Conservation Commission reviews Mass. Laborers’ request to move gas line
The Conservation Commission at its Tuesday night meeting continued a hearing on a request to move a gas line that previously prompted neighborhood concerns at the Mass. Laborers Training facility. Located at 37 East Street, the project has been discussed over the...
Conservation Commission split on decision to proceed with gas pipeline at Mass. Laborers facility
The Conservation Commission at its meeting Tuesday night approved 4-3 the notice of intent hearing on the Massachusetts Laborers Training facility’s initially proposed gas line under the Wetlands Protection Act, the preferred option of the developer, after some...
Conservation Commission hears alternatives for Mass. Laborers gas line plan
The Conservation Commission met for more than three hours Tuesday night and voted 6-0 to continue a notice of intent hearing on the Massachusetts Laborers Training facility’s proposed gas line so that alternative routes proposed during the hearing could be reviewed....
Laborers’ Training Center presents development details to Planning Board
The Planning Board met for more than three hours Monday night, as representatives from the Massachusetts Laborers’ Training Center gave an overview of their site construction plans, which include a new headquarters building and an updated dormitory. Attorney George...
ConCom OK’s utility work at Laborers Training Center, which seeks to expand
The Conservation Commission at its Tuesday meeting approved by a 5-0 vote a notice of intent (NOI) filed by the Massachusetts Laborers’ Training Trust Fund for utility work, subject to the submitting of paperwork and an order of conditions discussed during the...
Conservation Commission roundup: Laborers Training Center plans expansion; Aiken Park bridge to be stabilized
The Conservation Commission met for four hours on Tuesday night to consider a variety of projects, the highlights of which are included below. Laborers' Training Academy expansion A notice of intent (NOI) was filed by the Massachusetts Laborers' Training Trust Fund...