hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
10:06 am, Wednesday, September 23, 2026
57°F
80 %
Wind Gust: 13 mph
Clouds: 93%
Sunrise: 6:34 am
Sunset: 6:42 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Town: Main Street project contractor strikes another gas line after violating Dig Safe law

by | Aug 12, 2021 | Featured: News, News

The town announced Wednesday that the Main Street Corridor Project contractor, A.F. Amorello & Sons, struck an active gas line while doing work Monday near the intersection of Main Street and Pleasant Street.

Eversource Gas was notified and repaired the leak within a couple of hours. Road closures on Main Street and Pleasant Street were required.

According to the town, Amorello did not wait for Eversource to mark the lines before doing the work, as required by law.

“Massachusetts State law requires that a contractor contact Dig Safe at least 72 business hours (excluding weekends and legal holidays) prior to digging,” the town’s press release stated. “Once notified, Dig Safe will contact member utilities to come to the site and mark underground utility wires, cables and pipelines. Amorello reported that Dig Safe had been contacted, but they began excavating before Eversource Gas had marked out their lines. Although Amorello was aware that there were active gas lines in the area and they were excavating carefully, they hit the gas line.

“As a result of proceeding to excavate without waiting for Eversource Gas to mark their gas lines, it is the Town’s understanding that Eversource Gas is taking this incident seriously and will follow the appropriate protocols for violation of the Dig Safe law.

“The Town has reviewed this event with MassDOT for reassurance that they will not allow similar incidents to happen and that moving forward all rules required by Dig Safe will be followed.”

This is at least the third time a gas line has been hit as part of the project. On May 10, the downtown area was closed to vehicular traffic for about two hours after a line was struck at the corner of Main Street and Grove Street. And early on June 1, project workers struck a gas line on West Main Street. It was repaired quickly by Eversource.

0 Comments

Related Articles

Cemetery Commission decides not to apply for CPC funding

The Cemetery Commission on Monday decided not to apply for Community Preservation Act funding via the Community Preservation Committee because it has not yet spent its previous grant awards. Under the CPA, at least 10% of the funding raised must be allocated among...

Mike Whalen

Crews to repave, stripe section of Hayden Rowe Street

The Department of Public Works announced that J.H. Lynch & Sons will be out on Hayden Rowe Street starting Monday to complete road work. According to a notice sent by the DPW, crews conducted paving on Monday between 136-149 Hayden Rowe Street northbound and...

Charleswood Dirt

Main Street Corridor Project update: Work planned for drain manhole

Tasks for the Main Street Corridor are light for the next week, according to the latest update from the town. The main project listed for next week is work on a drain manhole at 63 Main Street. Crews will be completing miscellaneous work throughout the project as...

Road work sign

New I-90/I-495 ramp to open Saturday, overnight closures to continue

According to the latest update from the Massachusetts Department of Transportation, a new ramp at the Interstate 90/Interstate 495 interchange in Hopkinton is scheduled to open Saturday. A new I-90 westbound ramp to I-495 northbound is set to open Saturday morning....

MassDOT logo

Final preparations underway for Family Day

Organizer Pat O'Brien is optimistic about this Saturday's Hopkinton Family Day. "The weather's going to be nice," said O'Brien. "That's the main thing we're looking for." The Friends of Hopkinton, which organizes and runs Family Day annually, has been putting final...

Family Day fireworks
Key Storage 4.14.22