Change orders minimal for Charleswood School project

by | Aug 19, 2026 | Education, Featured: Education

The Elementary School Building Committee heard budget and construction updates about the Charleswood School during a brief meeting Tuesday.

Chris Kenney from owner’s project manager Vertex noted his company is tracking $523,371 in pending and estimated change orders — which amounts to 10% of the remaining construction contingency total.

ESBC member Bill Flannery asked where in the building cycle an “uptick” may be expected in change orders. Ten change orders submitted and approved totaled $90,381.

“The design team has done a good job to make sure that the design is well vetted,” Kenney replied.

Kenney said a lot of the major elements of unforeseen conditions would have come up by now, in his opinion. “The finishes are fairly straightforward, as all the other work is in place and has been verified and checked,” he said.

While major unforeseen items are unlikely, Kenney said, “minor coordination” issues could result in change orders.

Flannery noted, “It seems like we’re doing very well in the contingency bucket here.”

Flannery said he asked the question because he was curious if there was a “bit of a fluke” because of the timing of things. “But it sounds like things are going well in this area.”

Budget information reviewed

Commitments on the $158,422,394 school project amount to $122,382,545 (77%) to date.

Expenditures total $67,269,441.

During a breakdown of the budget, Kenney noted architect Perkins Eastman’s expenditures to date are about $9.5 million (78% of its $12.2 million contract value), while Vertex has spent approximately $2.5 million (50.8% of its $4.9 million contract value).

The general contractor, Brait Builders, has a current contract value of $103,281,387. The company has billed (less 5% retainage) $53,605,462.

Lynch, the contractor for roadway work, has a $1.4 million contract value and billings to date of $767,076.

Construction progress updated

Kenney told the committee that the Charleswood School project is on track to be completed by July 2027, a few months ahead of schedule.

He showed a series of work photographs depicting infiltration system excavation and subgrade preparation, sidewalk placement at the entry drive, interior stairs, wallboard in classrooms, low roof work, stormwater structures and more.

The work plan for next month includes installing drainage systems, loam and landscaping at entry roadways, roofing systems at low roofs, curtain wall systems and masonry veneers.

ESBC chair Jon Graziano said Vertex does a great job tracking and keeping him up to speed on what is going on at the site.

“We’re in good hands with our project managers,” he said.

0 Comments

Submit a Comment

Your email address will not be published. Required fields are marked *

Related Articles

Schools Notebook: Local collegians recognized

The University of Massachusetts announced its dean’s list recipients for the spring semester. Hopkinton residents recognized were Jahan Bahri, Marc Beauvais, Matthew Beauvais, Virendra Bhawsar, Julian Bianchi, Caleb Burke, Olivia Carrazza, Owen Champlin, Shivali...

Boston College

PBC chooses owner’s project manager for Center School project

The Permanent Building Committee on Monday voted 3-0 to select Vertex as the owner’s project manager for the Center School reuse project. Early estimates for the project went as high as $16.8 million, but some features were cut during design revisions in May that...

Center School

HHS students achieve high results on AP exams

On the most recent Advanced Placement tests, 96% of 619 Hopkinton High School students scored higher than the qualifying score of 3, with the average exam scores at 4.2 out of 5. The exams are offered in 25 subjects. At Thursday’s School Committee meeting, Sarah...

Hopkinton High School front entrance, Hillers H sign

School Committee tables study about moving modulars to Hopkins School

https://www.youtube.com/watch?v=n1qNkQPWaBc&list=PL8WekT6kxX1B3xlP6fIr3QmhJButK4GkU&index=1 The School Committee on Thursday voted to table a proposal to authorize $136,953 to study and develop a funding request for this fall’s expected Special Town Meeting...

Elmwood addition

Schools Notebook: Local collegians honored

A number of Hopkinton residents were named to the dean’s list for the spring semester at Worcester Polytechnic Institute. The list includes senior Mena Youssif (a civil engineering major), juniors Sofia Bilodeau (psychological science), Joseph Kane (mathematical...

Boston College
Key Storage 4.14.22