Change orders minimal for Charleswood School project

by | Aug 19, 2026 | Education, Featured: Education

The Elementary School Building Committee heard budget and construction updates about the Charleswood School during a brief meeting Tuesday.

Chris Kenney from owner’s project manager Vertex noted his company is tracking $523,371 in pending and estimated change orders — which amounts to 10% of the remaining construction contingency total.

ESBC member Bill Flannery asked where in the building cycle an “uptick” may be expected in change orders. Ten change orders submitted and approved totaled $90,381.

“The design team has done a good job to make sure that the design is well vetted,” Kenney replied.

Kenney said a lot of the major elements of unforeseen conditions would have come up by now, in his opinion. “The finishes are fairly straightforward, as all the other work is in place and has been verified and checked,” he said.

While major unforeseen items are unlikely, Kenney said, “minor coordination” issues could result in change orders.

Flannery noted, “It seems like we’re doing very well in the contingency bucket here.”

Flannery said he asked the question because he was curious if there was a “bit of a fluke” because of the timing of things. “But it sounds like things are going well in this area.”

Budget information reviewed

Commitments on the $158,422,394 school project amount to $122,382,545 (77%) to date.

Expenditures total $67,269,441.

During a breakdown of the budget, Kenney noted architect Perkins Eastman’s expenditures to date are about $9.5 million (78% of its $12.2 million contract value), while Vertex has spent approximately $2.5 million (50.8% of its $4.9 million contract value).

The general contractor, Brait Builders, has a current contract value of $103,281,387. The company has billed (less 5% retainage) $53,605,462.

Lynch, the contractor for roadway work, has a $1.4 million contract value and billings to date of $767,076.

Construction progress updated

Kenney told the committee that the Charleswood School project is on track to be completed by July 2027, a few months ahead of schedule.

He showed a series of work photographs depicting infiltration system excavation and subgrade preparation, sidewalk placement at the entry drive, interior stairs, wallboard in classrooms, low roof work, stormwater structures and more.

The work plan for next month includes installing drainage systems, loam and landscaping at entry roadways, roofing systems at low roofs, curtain wall systems and masonry veneers.

ESBC chair Jon Graziano said Vertex does a great job tracking and keeping him up to speed on what is going on at the site.

“We’re in good hands with our project managers,” he said.

0 Comments

Related Articles

DPW leaders describe department constraints to WSAB

The Water and Sewer Advisory Board on Nov. 18 heard from senior staff at the Department of Public Works on the challenges it faces while providing Hopkinton with water and sewer services. DPW Director Kerry Reed and Water & Sewer Manager Jed Fenneuff told the...

PFAS filtration system at Well #6

Charleswood School project continues ahead of schedule

During a brief meeting of the Elementary School Building Committee on Tuesday, members got updates on work progress, the budget, the schedule and next steps. Chris Kenney, project manager at Vertex, reported the $158 million project remains ahead of schedule, with...

Charleswood construction

School Committee approves capital plan

During a brief Zoom meeting Friday, the School Committee unanimously approved a revised fiscal year 2028 capital plan that includes requests totaling $545,000 as well as $22.4 million for a geothermal heat, ventilation and air conditioning system at the high...

Hopkinton Public Schools Administration sign

Health survey of local students shows encouraging trend

Hopkinton’s middle and high school students are feeling less anxious and depressed, but there still are areas of concern, particularly for students with disabilities and in the LGBTQ+ community. At this past Thursday's School Committee meeting, the results of the...

Hopkinton Middle School

Crews to work on Charleswood water main Wednesday

Water-Sewer Department manager Jed Fenneuff announced that construction crews will perform work on the new water main for Charleswood School on Wednesday. According to Fenneuff, the work will begin at 9 a.m. He noted that residents nearby on Hayden Rowe Street may...

Charleswood Construction

Water discoloration possible due to Charleswood work

The Water-Sewer Department announced that continued work related to the Charleswood School project may impact nearby water quality. According to a notice from Water-Sewer Manager Jed Fenneuff, residents in the area of the project on Hayden Rowe Street may...

Charleswood Construction
Key Storage 4.14.22