As part of the Main Street Corridor Project this week, crews will form and pour sidewalks between Muffin House Cafe and Ash Street, pave the top mix on the bike lane, place loam in various areas and perform various on-site cleanup in the same area.
On the west side of the project, workers will install posts for crosswalk beacons at Pleasant Street and Commonwealth Avenue, place loam in various areas and perform various on-site cleanup.
Working hours for the Main Street Corridor Project are 7 a.m. until 3 p.m. No detours, one-lane closures or road closures are allowed from 7-9 a.m.
This schedule may change due to weather and existing conditions found while performing the planned tasks. For the most up-to-date information, visit the town’s project website at hopkintonmainstreet.com.