hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
6:19 pm, Tuesday, September 22, 2026
57°F
60 %
Wind Gust: 9 mph
Clouds: 58%
Sunrise: 6:33 am
Sunset: 6:44 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: Construction meeting held; transformers still not available

by | Jan 26, 2024 | Business, News

The town issued a press release Friday with updates about the Main Street Corridor Project following a construction meeting that was held Tuesday.

At the meeting were representatives from the town, engineering consultant VHB, the Massachusetts Department of Transportation (MassDOT), project contractor Amorello and Eversource.

Amorello has not set a time for returning to the project, according to the press release. Utility work, including both overhead and underground work, needs to be completed before Amorello will be able to schedule any work.

Eversource continues to await the transformers, stating that there is no new information available. The utility company anticipates starting the transfer of overhead electrical lines to the new utility poles in about a month, although no definitive date has been set. MassDOT confirmed that a utility meeting will be held once a date is confirmed.

When the transfer of overhead utilities is complete, the old poles will be removed. This will allow work to be completed from Wood Street to the Fire Station, where the utilities are not being undergrounded.

Amorello will not be able to continue work from the Fire Station to Ash Street until Eversource is able to complete the underground portion of the project in this area.

Regarding complaints about peeling paint on the new signal poles, MassDOT is reviewing another repair-in-place process from the manufacturer to determine if the process is acceptable. It will need to be field tested before final approval. The town noted that replacement is preferred.

Weekly construction advisories will resume when there are weekly updates on the project. Until then, the town will send project updates as needed.

0 Comments

Related Articles

Cemetery Commission decides not to apply for CPC funding

The Cemetery Commission on Monday decided not to apply for Community Preservation Act funding via the Community Preservation Committee because it has not yet spent its previous grant awards. Under the CPA, at least 10% of the funding raised must be allocated among...

Mike Whalen

Crews to repave, stripe section of Hayden Rowe Street

The Department of Public Works announced that J.H. Lynch & Sons will be out on Hayden Rowe Street starting Monday to complete road work. According to a notice sent by the DPW, crews conducted paving on Monday between 136-149 Hayden Rowe Street northbound and...

Charleswood Dirt

Main Street Corridor Project update: Work planned for drain manhole

Tasks for the Main Street Corridor are light for the next week, according to the latest update from the town. The main project listed for next week is work on a drain manhole at 63 Main Street. Crews will be completing miscellaneous work throughout the project as...

Road work sign

New I-90/I-495 ramp to open Saturday, overnight closures to continue

According to the latest update from the Massachusetts Department of Transportation, a new ramp at the Interstate 90/Interstate 495 interchange in Hopkinton is scheduled to open Saturday. A new I-90 westbound ramp to I-495 northbound is set to open Saturday morning....

MassDOT logo
Key Storage 4.14.22