hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
8:17 pm, Wednesday, April 22, 2026
43°F
68 %
Wind Gust: 19 mph
Clouds: 100%
Sunrise: 5:54 am
Sunset: 7:34 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: All 12 transformers installed

by | Aug 24, 2024 | Featured: News, News

Transformers on Main Street

Workers install transformers on Main Street on Thursday. PHOTO/JOHN CARDILLO

The town on Friday issued an update on the Main Street Corridor Project, announcing that all 12 transformers have been installed.

The receipt of the transformers had been delayed for months by supply chain issues. After a push in June by Select Board chair Brian Herr, six transformers arrived in mid-July. The remaining six arrived in early August.

Eversource crews have been performing the preliminary work associated with the transformers, which should be completed within a month. Shifting power lines from being overhead to underground should begin in late September or early October.

Overhead utility line work will continue on the west side of the project during the upcoming week, while work on underground utility connections from property lines to building foundations also continues.

Polar Vortex’s painting crew will continue its work on the traffic poles, where paint was peeling. Scheduled hours for this work will be from 7 a.m. until 5 p.m. Locations for repairs include the intersections of Main Street and Commonwealth Avenue, Pleasant Street, Grove Street, Church Street, Wood Street and Hayden Rowe Street, as well as in front of the Fire Station.

A.F. Amorello & Sons, the project’s construction company, is expected to return to work on the project during the upcoming week. The company has been performing brickwork, sidewalk work, curb work, landscaping and underground utility connections from the property lines to several building foundations and into buildings as required.

This schedule may change due to weather and existing conditions found while performing these tasks. This work may impact traffic and require lane and sidewalk closures, limiting access to driveways and entrances to businesses. Detours and alternating traffic patterns may be used as necessary.

Transformers on Main Street

A transformer sits underground after having been installed Thursday. PHOTO/JOHN CARDILLO

0 Comments

Related Articles

Arrests/Police Log, April 22 edition

ARRESTS None this week.   POLICE LOG April 14 6:35 a.m. A walk-in handed in a debit card found at Middlesex Savings Bank on Main Street. 8:41 a.m. A caller reported a vehicle sped past a school bus with its stop sign out on Hayward Street. Sgt. Matthew Santoro...

Hopkinton police cruiser

DPW to start sidewalk construction on Chestnut Street Tuesday

The Department of Public Works announced last week that contractors are scheduled to begin construction of a sidewalk on Chestnut Street starting Tuesday. Along the southern side of Chestnut Street between Wild Road and Smith Road, the DPW plans to construct a...

Main Street bike lane

HPD Chief Bennett to retire June 30, ending 35-year career

Hopkinton Police Chief Joseph Bennett announced Friday in a press release that he will retire June 30. Bennett’s retirement caps 35 years of police service, nearly all of which he spent in Hopkinton. His law enforcement journey began in 1991 when he became a...

Boston Marathon
Key Storage 4.14.22