hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
4:00 am, Tuesday, October 13, 2026
55°F
94 %
Wind Gust: 2 mph
Clouds: 100%
Sunrise: 6:56 am
Sunset: 6:08 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: All 12 transformers installed

by | Aug 24, 2024 | Featured: News, News

Transformers on Main Street

Workers install transformers on Main Street on Thursday. PHOTO/JOHN CARDILLO

The town on Friday issued an update on the Main Street Corridor Project, announcing that all 12 transformers have been installed.

The receipt of the transformers had been delayed for months by supply chain issues. After a push in June by Select Board chair Brian Herr, six transformers arrived in mid-July. The remaining six arrived in early August.

Eversource crews have been performing the preliminary work associated with the transformers, which should be completed within a month. Shifting power lines from being overhead to underground should begin in late September or early October.

Overhead utility line work will continue on the west side of the project during the upcoming week, while work on underground utility connections from property lines to building foundations also continues.

Polar Vortex’s painting crew will continue its work on the traffic poles, where paint was peeling. Scheduled hours for this work will be from 7 a.m. until 5 p.m. Locations for repairs include the intersections of Main Street and Commonwealth Avenue, Pleasant Street, Grove Street, Church Street, Wood Street and Hayden Rowe Street, as well as in front of the Fire Station.

A.F. Amorello & Sons, the project’s construction company, is expected to return to work on the project during the upcoming week. The company has been performing brickwork, sidewalk work, curb work, landscaping and underground utility connections from the property lines to several building foundations and into buildings as required.

This schedule may change due to weather and existing conditions found while performing these tasks. This work may impact traffic and require lane and sidewalk closures, limiting access to driveways and entrances to businesses. Detours and alternating traffic patterns may be used as necessary.

Transformers on Main Street

A transformer sits underground after having been installed Thursday. PHOTO/JOHN CARDILLO

0 Comments

Related Articles

Midweek ramp closures at I-90/I-495 interchange start Tuesday night

More overnight ramp closures at the Interstate 90/Interstate 495 interchange in Hopkinton will take place this week starting Tuesday and continuing into Thursday, according to the Massachusetts Department of Transportation. Starting Tuesday night, MassDOT plans to...

MassDOT logo

Authorities investigate death at Golden Pond, find heating issues

Multiple state and local agencies are investigating an unattended death that occurred at Golden Pond Assisted Living on Sept. 30 following questions about the temperature of the individual’s living space at the time and the overall function of the facility’s...

Golden Pond sign

Arrests/Police Log, Oct. 7 edition

ARRESTS Oct. 3 1:40 a.m. Units stopped a vehicle on Hayden Rowe Street and conducted a field sobriety test. A 37-year-old man from Walpole was taken into custody and charged with using an electronic device while operating a motor vehicle, speeding at a rate of...

Hopkinton police cruiser

Roadwork on Smith Road scheduled to begin next week

Scheduled work on Smith Road is set to begin next week, according to a recent notice from the Department of Public Works. Hopkinton highway manager Mike Mansir stated in a notice to residents that construction on Smith Road will begin Oct. 14. Work hours are...

Hayden Rowe roadwork
Key Storage 4.14.22