hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
8:45 pm, Tuesday, June 9, 2026
71°F
56 %
Wind Gust: 28 mph
Clouds: 95%
Sunrise: 5:09 am
Sunset: 8:21 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: Brick installation to begin in late August after mock-up receives approval

by | Aug 16, 2024 | Featured: News, News

The town on Friday issued an update on the Main Street Corridor Project, noting that the brick mock-up was approved so that work can be done to prepare for installation slated to begin in late August.

The brick mock-up in front of Town Hall was completed on Aug. 12. Town staff met with representatives from the Massachusetts Department of Transportation and A. F. Amorello & Sons, the project’s construction company. They confirmed the brick color, pattern and layout are per the MassDOT plan, and the mock-up was approved. The mock-up remained in front of Town Hall for a few days for public viewing.

Now that the mock-up has received approval, Amorello and its subcontractor provided a tentative schedule for starting the brick work during the week of Aug. 26. The work will include the installation of the brick inlay portion of the project throughout the corridor. Saw cutting of the cement sidewalk and the asphalt bike lane will be performed in preparation for the brick installation.

The outstanding features for the project appear to be coming together. The final six transformers of the 12 necessary to complete the project were received from Eversource in early August. They are in the testing phase, and no issues are anticipated.

Three of the six transformers initially delivered were installed by Eversource on July 25 in the vicinity of the Town Common. All six were received earlier that week. It is unclear when the remaining transformers will be installed.

The receipt of the transformers had been delayed for months by supply chain issues.

Overhead utility line work will continue on the west side of the project during the upcoming week, while work on underground utility connections from property lines to building foundations also continues.

Polar Vortex’s painting crew will continue its work on the traffic poles, repairing peeling paint. Scheduled hours for this work will be from 7 a.m. to 5 p.m. Locations for repairs include the intersections of Main Street and Commonwealth Avenue, Pleasant Street, Grove Street, Church Street, Wood Street and Hayden Rowe Street, as well as in front of the Fire Station.

This schedule may change due to weather and existing conditions found while performing these tasks. This work may impact traffic and require lane and sidewalk closures, limiting access to driveways and entrances to businesses. Detours and alternating traffic patterns may be used as necessary.

0 Comments

Related Articles

Commission on Disability talks policy with town ADA coordinator

The Commission on Disability on Monday discussed accessibility issues in town with Christopher McWhite, the town’s ADA coordinator. McWhite told commissioners about his extensive background in this field. He has done this type of work for about 27 years across five...

Commission on Disability

Contractors to begin Claflin Place drainage work next week

The town announced on Monday that contractors are set to begin working on the Claflin Place drainage project on June 15. According to a notice from the town, work will start at the top of the road near Main Street and move south down Claflin Place. There will be no...

Water main break
Key Storage 4.14.22