Main Street Corridor Project update: Eastbound detour at Grove Street to be used as needed this week

by | Dec 18, 2022 | News

As part of the Main Street Corridor Project this week, the eastbound detour from Grove Street to Maple Street to Hayden Rowe Street and back to Main Street will be used on an as-needed basis.

Project-wide, the contractor will patch around structures and do a final cleanup and winterizing. Eversource will perform underground utility work (up to property lines only).

On the east side of the project, workers will continue underground service connections between Muffin House Cafe and Church Street.

Working hours for the Main Street Corridor Project are 7 a.m. until 3 p.m. No detours, one-lane closures or road closures are allowed from 7-9 a.m.

This schedule may change due to weather and existing conditions found while performing the planned tasks. For the most up-to-date information, visit the town’s project website at hopkintonmainstreet.com.

0 Comments

Related Articles

Main Street Corridor Project update: Walkway work continues

The town’s latest Main Street Corridor Project update released Friday shared that walkway work will resume on Main Street during the upcoming week. Addresses affected by this work include 35, 36 and 77 Main Street. Miscellaneous work also will continued along the...

Main Street brickwork
Key Storage 4.14.22