hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
8:00 am, Thursday, September 24, 2026
46°F
93 %
Wind Gust: 11 mph
Clouds: 0%
Sunrise: 6:35 am
Sunset: 6:40 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project update: Eastbound detour returns; paving of intersection scheduled

by | Aug 28, 2022 | News

As part of the Main Street Corridor Project this week, the contractor will continue work at the intersection of Route 135 and Route 85, with the eastbound detour remaining in place.

The contractor will continue grading the road at the intersection from 6 a.m. to 7 p.m. on Monday only. Road paving will take place from 7 a.m. to 5 or 6 p.m. and is expected to take two days. Temporary traffic markings on the newly paved area are estimated to take place in the middle or end of the week.

The detour will send eastbound traffic from Main Street to Pleasant Street to Maple Street to Hayden Rowe Street and back to Main Street. Walcott Street will be open to two-way traffic during the detour and will revert to one-way traffic when Main Street is reopened.

Other work being performed this week includes Comcast duct work from Muffin House to the east end of the project limit as well as service connections project-wide. On the west side of the project — working eastbound from the Wood Street intersection toward the Fire Station — the contractor will continue to install new granite curbs, fine grade and compact sidewalks, and start forming concrete sidewalks mainly on the south side of the road. Concrete sidewalk work will be at the end of driveways; affected property owners will be notified in advance as driveway access will be impacted. Emergency vehicle access will be maintained.

This schedule may change due to weather and existing conditions found while performing the planned tasks. For the most up-to-date information, visit the town’s project website at hopkintonmainstreet.com.

0 Comments

Related Articles

Arrests/Police Log, Sept. 23 edition

ARRESTS Sept. 18 8:35 p.m. Officers conducted a straight warrant arrest on West Main Street of a 26-year-old female from South Yarmouth. [Editor’s note: The Hopkinton Independent’s policy for the arrests section is not to include the names of individuals who have...

Hopkinton police cruiser

Cemetery Commission decides not to apply for CPC funding

The Cemetery Commission on Monday decided not to apply for Community Preservation Act funding via the Community Preservation Committee because it has not yet spent its previous grant awards. Under the CPA, at least 10% of the funding raised must be allocated among...

Mike Whalen

Crews to repave, stripe section of Hayden Rowe Street

The Department of Public Works announced that J.H. Lynch & Sons will be out on Hayden Rowe Street starting Monday to complete road work. According to a notice sent by the DPW, crews conducted paving on Monday between 136-149 Hayden Rowe Street northbound and...

Charleswood Dirt
Key Storage 4.14.22