Main Street Corridor Project update: Pleasant Street, Town Common detours resume this week

by | Sep 18, 2022 | News

As part of the Main Street Corridor Project, work this week will include raising castings on manholes project-wide. The eastbound detour from Main Street to Pleasant Street to Maple Street to Hayden Rowe Street and back to Main Street will be utilized.

Additionally, conduit work on Hayden Rowe Street will necessitate a detour for southbound traffic around the Town Common via Ash Street to Park Street and back to Hayden Rowe. Northbound traffic will not be impacted.

Other work on the east side of the project will include Comcast duct bank work at Church Street and Walcott Street (expected to be one day for each location), electric conduit work at Ash Street, and continued work on on service connections up to property lines from Muffin House to Ash Street.

At the Route 135/Route 85 intersection, the contractor will continue grading, compacting, forming and pouring sidewalks between Wood Street and the Fire Station.

This schedule may change due to weather and existing conditions found while performing the planned tasks. For the most up-to-date information, visit the town’s project website at hopkintonmainstreet.com.

0 Comments

Related Articles

Library, Parks & Rec directors set to depart jobs

Three key leaders in town positions will be leaving Hopkinton within next two weeks, the Independent has learned. Nanci Hill, the Hopkinton Public Library’s director, submitted her resignation letter on Aug. 27. According to the library’s website, the position will...

Nanci Hill
Key Storage 4.14.22