hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
3:59 pm, Tuesday, September 22, 2026
62°F
57 %
Wind Gust: 20 mph
Clouds: 69%
Sunrise: 6:33 am
Sunset: 6:44 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street project moves toward undergrounding phase

by | Aug 29, 2021 | Featured: News, News

The town announced Friday that drainage work for the Main Street Corridor Project was nearing completion and preparation is underway for the next phase, which includes work related to the undergrounding of utilities.

The undergrounding work will begin with the installation of six underground electric manholes (vaults) on Main Street between Wood Street and the intersection of Route 85 and Main Street, the town explained. The vaults, which range in size, will require excavation of pits as large as 15 feet by 11 feet. The installation of each vault is scheduled to take three days.

A town press release indicated that contractor A.F. Amorello had hoped to shut down Main Street for several days, setting up detours, but the town “rejected that plan, and all parties have worked together to update the schedule of operations for this work.”

The new plan has the contractor working Monday through Friday from 7 a.m.-3 p.m. — with the possibility of extending the hours to as late as 7 p.m. if needed to keep the schedule on track. No weekend work is anticipated.

There will be no detours, and Main Street will remain open at all times, with at least one lane of alternating traffic around the work sites. Drivers are encouraged to seek alternate routes.

The undergrounding work is anticipated to begin within 2-3 weeks and could take 4-6 weeks to complete.

0 Comments

Related Articles

Cemetery Commission decides not to apply for CPC funding

The Cemetery Commission on Monday decided not to apply for Community Preservation Act funding via the Community Preservation Committee because it has not yet spent its previous grant awards. Under the CPA, at least 10% of the funding raised must be allocated among...

Mike Whalen

Crews to repave, stripe section of Hayden Rowe Street

The Department of Public Works announced that J.H. Lynch & Sons will be out on Hayden Rowe Street starting Monday to complete road work. According to a notice sent by the DPW, crews conducted paving on Monday between 136-149 Hayden Rowe Street northbound and...

Charleswood Dirt

Main Street Corridor Project update: Work planned for drain manhole

Tasks for the Main Street Corridor are light for the next week, according to the latest update from the town. The main project listed for next week is work on a drain manhole at 63 Main Street. Crews will be completing miscellaneous work throughout the project as...

Road work sign

New I-90/I-495 ramp to open Saturday, overnight closures to continue

According to the latest update from the Massachusetts Department of Transportation, a new ramp at the Interstate 90/Interstate 495 interchange in Hopkinton is scheduled to open Saturday. A new I-90 westbound ramp to I-495 northbound is set to open Saturday morning....

MassDOT logo

Final preparations underway for Family Day

Organizer Pat O'Brien is optimistic about this Saturday's Hopkinton Family Day. "The weather's going to be nice," said O'Brien. "That's the main thing we're looking for." The Friends of Hopkinton, which organizes and runs Family Day annually, has been putting final...

Family Day fireworks
Key Storage 4.14.22