hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
12:48 am, Wednesday, July 22, 2026
70°F
95 %
Wind Gust: 4 mph
Clouds: 100%
Sunrise: 5:29 am
Sunset: 8:15 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street project moves toward undergrounding phase

by | Aug 29, 2021 | Featured: News, News

The town announced Friday that drainage work for the Main Street Corridor Project was nearing completion and preparation is underway for the next phase, which includes work related to the undergrounding of utilities.

The undergrounding work will begin with the installation of six underground electric manholes (vaults) on Main Street between Wood Street and the intersection of Route 85 and Main Street, the town explained. The vaults, which range in size, will require excavation of pits as large as 15 feet by 11 feet. The installation of each vault is scheduled to take three days.

A town press release indicated that contractor A.F. Amorello had hoped to shut down Main Street for several days, setting up detours, but the town “rejected that plan, and all parties have worked together to update the schedule of operations for this work.”

The new plan has the contractor working Monday through Friday from 7 a.m.-3 p.m. — with the possibility of extending the hours to as late as 7 p.m. if needed to keep the schedule on track. No weekend work is anticipated.

There will be no detours, and Main Street will remain open at all times, with at least one lane of alternating traffic around the work sites. Drivers are encouraged to seek alternate routes.

The undergrounding work is anticipated to begin within 2-3 weeks and could take 4-6 weeks to complete.

0 Comments

Related Articles

Water main on Hayden Rowe Street to shut down Wednesday morning

A portion of the water main on Hayden Rowe Street will be shut down Wednesday morning, according to the Water-Sewer Department. In a notice to residents, Water-Sewer Manager Jed Fenneuff stated that a water main on Hayden Rowe Street will be shut down from 9 a.m.-1...

Fire hydrant on Pleasant Street

Ramp closures at I-90/I-495 interchange planned for Wednesday

The Massachusetts Department of Transportation will close two ramps at the Interstate 90/Interstate 495 interchange in Hopkinton Wednesday night to facilitate construction operations. Both the I-90 eastbound ramp to I-495 northbound (Exit 106) and the I-495...

MassDOT logo

Main Street Corridor Project update: Subdrain work continues

A.F. Amorello & Sons will be back next week to continue installing a subdrain, according to the latest Main Street Corridor Project update. The subdrain is being installed on the north side of Main Street between the driveway of 7 Main Street (east of the...

Road work sign
Key Storage 4.14.22