hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
3:58 am, Wednesday, September 23, 2026
46°F
91 %
Wind Gust: 5 mph
Clouds: 99%
Sunrise: 6:34 am
Sunset: 6:42 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Pre-construction meeting held for Main Street Corridor Project

by | Jan 8, 2021 | News

The town announced Friday that a pre-construction meeting for the Main Street Corridor Project was held Thursday, bring together representatives from town departments, the Massachusetts Department of Transportation (MassDOT), contractor A.F. Amorello & Sons, Inc., public outreach firm City Point Partners, town engineering consultant VHB, and utility companies.

Via press release, the town summed up the meeting as follows:

“MassDOT announced during the meeting that [its] survey crew is scheduled to be back onsite, weather permitting, starting on Tuesday, January 19th. They are scheduled to complete the right-of-way survey and start laying out project easements. The survey of the easements will require MassDOT survey personnel to work on private property.

“Project Manager Tobias Pawlak-Silva, of A.F. Amorello & Sons, Inc. presented a preliminary construction schedule showing a construction crew starting work on the east side of the project (Ash Street to Route 85 intersection). The work will commence as early as weather permits, which could possibly be as early as March. The schedule also showed a second crew starting on the west side of the project (Wood Street to Route 85 intersection) shortly after the first crew started.

“Announcing the start of the construction for this project is a long awaited milestone,” said Town Manager Norman Khumalo. “We can now look forward to realizing the many benefits that will result from its completion.

“Also discussed at the meeting was the importance of the public outreach plan. Maintaining effective, two-way communication with stakeholders and abutters is an important goal of this project and will be achieved through continued and consistent community engagement. Public outreach for the project will be a coordinated effort between the town, VHB, MassDOT, the contractor, and the public outreach firm, City Point Partners, and will include a dedicated Main Street Corridor Project website which will be updated on a weekly basis. A future press release will announce the formal launch of the project website.”

0 Comments

Related Articles

Cemetery Commission decides not to apply for CPC funding

The Cemetery Commission on Monday decided not to apply for Community Preservation Act funding via the Community Preservation Committee because it has not yet spent its previous grant awards. Under the CPA, at least 10% of the funding raised must be allocated among...

Mike Whalen

Crews to repave, stripe section of Hayden Rowe Street

The Department of Public Works announced that J.H. Lynch & Sons will be out on Hayden Rowe Street starting Monday to complete road work. According to a notice sent by the DPW, crews conducted paving on Monday between 136-149 Hayden Rowe Street northbound and...

Charleswood Dirt

Main Street Corridor Project update: Work planned for drain manhole

Tasks for the Main Street Corridor are light for the next week, according to the latest update from the town. The main project listed for next week is work on a drain manhole at 63 Main Street. Crews will be completing miscellaneous work throughout the project as...

Road work sign

New I-90/I-495 ramp to open Saturday, overnight closures to continue

According to the latest update from the Massachusetts Department of Transportation, a new ramp at the Interstate 90/Interstate 495 interchange in Hopkinton is scheduled to open Saturday. A new I-90 westbound ramp to I-495 northbound is set to open Saturday morning....

MassDOT logo

Final preparations underway for Family Day

Organizer Pat O'Brien is optimistic about this Saturday's Hopkinton Family Day. "The weather's going to be nice," said O'Brien. "That's the main thing we're looking for." The Friends of Hopkinton, which organizes and runs Family Day annually, has been putting final...

Family Day fireworks
Key Storage 4.14.22