hopkinton-independent-logo2x
Hopkinton, MA
loader-image
Hopkinton, US
11:36 am, Tuesday, September 22, 2026
61°F
69 %
Wind Gust: 9 mph
Clouds: 54%
Sunrise: 6:33 am
Sunset: 6:44 pm

SIGN UP TODAY!
BREAKING NEWS & DAILY NEWSLETTER





Main Street Corridor Project: Undergrounding of utilities begins Monday

by | Oct 15, 2021 | Featured: News, News

Main Street Construction Project map 10-15-21

This map indicates the area that will be affected by the upcoming week’s work.

The town announced Friday that the installation of the first electric manhole vault as part of the Main Street Corridor Project will begin Monday near the intersection of Main Street and Claflin Avenue (between 102 and 104 Main Street).

The town’s press release states:

The work Monday will require a lane shift to maintain two lanes of traffic. Police details will be present 24 hours a day as the work will require several days to complete while the excavation pit remains open with Jersey barriers installed around the open excavation. Work hours during the day will remain 7 a.m.-3 p.m. but may be extended if necessary. Temporary lighting is proposed overnight for the protection of detail officers and for vehicle safety traveling through the shifted lane overnight. The plan provides two lanes of traffic through the work area delineated by cones or barrels. There may be the need to temporarily go down to one lane of alternating traffic for short periods of time.

Abutters who will have their driveway access limited or blocked are to be contacted by the town and contractor in the next few days.

0 Comments

Related Articles

Cemetery Commission decides not to apply for CPC funding

The Cemetery Commission on Monday decided not to apply for Community Preservation Act funding via the Community Preservation Committee because it has not yet spent its previous grant awards. Under the CPA, at least 10% of the funding raised must be allocated among...

Mike Whalen

Crews to repave, stripe section of Hayden Rowe Street

The Department of Public Works announced that J.H. Lynch & Sons will be out on Hayden Rowe Street starting Monday to complete road work. According to a notice sent by the DPW, crews conducted paving on Monday between 136-149 Hayden Rowe Street northbound and...

Charleswood Dirt

Main Street Corridor Project update: Work planned for drain manhole

Tasks for the Main Street Corridor are light for the next week, according to the latest update from the town. The main project listed for next week is work on a drain manhole at 63 Main Street. Crews will be completing miscellaneous work throughout the project as...

Road work sign

New I-90/I-495 ramp to open Saturday, overnight closures to continue

According to the latest update from the Massachusetts Department of Transportation, a new ramp at the Interstate 90/Interstate 495 interchange in Hopkinton is scheduled to open Saturday. A new I-90 westbound ramp to I-495 northbound is set to open Saturday morning....

MassDOT logo

Final preparations underway for Family Day

Organizer Pat O'Brien is optimistic about this Saturday's Hopkinton Family Day. "The weather's going to be nice," said O'Brien. "That's the main thing we're looking for." The Friends of Hopkinton, which organizes and runs Family Day annually, has been putting final...

Family Day fireworks
Key Storage 4.14.22