As part of the Main Street Corridor Project this week, crews will grade the bike path between the Muffin House Cafe and Hayden Rowe Street and perform various on-site cleanup work.
On the west side of the project, the focus will be on installing foundations and posts for crosswalk beacons at Pleasant Street and Commonwealth Avenue.
Working hours for the Main Street Corridor Project are 7 a.m. until 3 p.m. No detours, one-lane closures or road closures are allowed from 7-9 a.m.
This schedule may change due to weather and existing conditions found while performing the planned tasks. For the most up-to-date information, visit the town’s project website at hopkintonmainstreet.com.