As part of the Main Street Corridor Project, work this week will include raising castings on manholes project-wide. The eastbound detour from Main Street to Pleasant Street to Maple Street to Hayden Rowe Street and back to Main Street will be utilized.
Additionally, conduit work on Hayden Rowe Street will necessitate a detour for southbound traffic around the Town Common via Ash Street to Park Street and back to Hayden Rowe. Northbound traffic will not be impacted.
Other work on the east side of the project will include Comcast duct bank work at Church Street and Walcott Street (expected to be one day for each location), electric conduit work at Ash Street, and continued work on on service connections up to property lines from Muffin House to Ash Street.
At the Route 135/Route 85 intersection, the contractor will continue grading, compacting, forming and pouring sidewalks between Wood Street and the Fire Station.
This schedule may change due to weather and existing conditions found while performing the planned tasks. For the most up-to-date information, visit the town’s project website at hopkintonmainstreet.com.