As part of the Main Street Corridor Project this week, there will be no work on Monday, Tuesday or Wednesday, as Hopkinton Town Hall and municipal offices are closed in observance of Independence Day. On the east side of the project, crews will continue installation...
Main Street Corridor Project
Main Street Corridor Project update: Work continues on site lighting, sidewalks
As part of the Main Street Corridor Project this week, workers will continue installation of conduit and bases for site lighting from Muffin House Cafe to Ash Street (work will take place in the excavated sidewalk area). Additionally, crews will work on installation...
Main Street Corridor Project update: Eastbound detour to be used as needed this week
As part of the Main Street Corridor Project this week, there will be no work on Monday in observance of the Juneteenth holiday. For the rest of the week, the eastbound detour from Grove Street to Maple Street to Hayden Rowe Street may be used as needed. On the east...
Main Street Corridor Project update: Eastbound detours all week
As part of the Main Street Corridor Project this week, the eastbound detour from Grove Street to Maple Street to Hayden Rowe Street will be used Monday through Friday. The eastbound detour from Pleasant Street to Maple Street to Hayden Rowe Street might be needed for...
Main Street Corridor Project update: Eastbound detours in place this week
As part of the Main Street Corridor Project this week, the eastbound detour from Pleasant Street to Maple Street to Hayden Rowe Street will be used at the beginning of the week, while the eastbound detour from Grove Street to Maple Street to Hayden Rowe Street will be...
Main Street Corridor Project update: Eastbound detours possible this week
As part of the Main Street Corridor Project this week, there will be no work on Monday (Memorial Day). The eastbound detour from Grove Street to Maple Street to Hayden Rowe Street might be used Tuesday through Friday. On the east side of the project, workers will...
Main Street Corridor Project update: Main Street paving this week; detours planned
As part of the Main Street Corridor Project this week, crews will begin the paving of Main Street from the Muffin House Cafe to Ray Street. The work is anticipated to take three days and is weather dependent. To expedite the work, public safety has approved a 7 a.m....
Main Street Corridor Project update: Full-depth excavation continues, detours all week
As part of the Main Street Corridor Project this week, construction crews will continue the full-depth excavation on the sidewalks and roadway on the east side of the project along with placement of gravel and dense graded crushed stone. The eastbound detour from...
Main Street Corridor Project update: Full-depth excavation starts Monday; detours all week
As part of the Main Street Corridor Project this week, the town announced that Phase 3 of full-depth excavation from Muffin House Cafe to the east end of the project begins Monday and is expected to take three weeks to complete. To expedite this work, public safety...
Main Street Corridor Project update: Full-depth excavation starts Monday
As part of the Main Street Corridor Project next week, the town announced that Phase 3 of full-depth excavation from Muffin House Cafe to the east end of the project begins Monday, May 8, and is expected to take three weeks to complete. Full-depth excavation includes...
Main Street Corridor Project update: Eastbound detour all week
As part of the Main Street Corridor Project this week, the eastbound detour from Pleasant Street to Maple Street to Grove Street will be used from Monday to Friday. The eastbound detour from Grove Street to Maple Street to Hayden Rowe Street may be used as needed. On...
Main Street Corridor Project update: Eastbound detour from Pleasant Street to Grove Street all week
As part of the Main Street Corridor Project this week, the eastbound detour from Pleasant Street to Maple Street to Grove Street will be used from Monday to Friday. On the east side of the project, crews will work on service connections to buildings between Muffin...
Main Street Corridor Project update: Work resumes Tuesday
As part of the Main Street Corridor Project this week, work will begin on Tuesday to continue the service connections to buildings between Muffin House Cafe and Hayden Rowe Street. Connections inside these buildings will take place on a future date. No work will be...
Main Street Corridor Project update: Line striping scheduled for Monday
As part of the Main Street Corridor Project this week, temporary line striping is to be applied from Grove Street to Ray Street beginning at 8 a.m. Monday. No other work is planned for the two weeks prior to the April 17 Boston Marathon. The contractor will commence...
Main Street Corridor Project update: Road paving set to begin Wednesday
As part of the Main Street Corridor Project this week, crews are scheduled to begin paving work Wednesday in preparation for the Boston Marathon. The work will take place on the east side of the project only — from Grove Street to Ray Street. The eastbound detour from...
Main Street Corridor Project update: Paving for Boston Marathon expected to start week of April 3
The town announced Friday that paving in preparation for the Boston Marathon is anticipated to start the week of April 3. The work is expected to take one day for milling, followed by one day of paving. Temporary markings will be done at night after the paving is...
Main Street Corridor Project update: Construction work done for season, to restart after Boston Marathon
The town announced Friday that the Main Street Corridor Project contractor, A.F. Amorello & Sons, has finished work for the season. Work will resume after the 2023 Boston Marathon. Marathon Way — the road between the Town Common and the doughboy statue — will be...
Discussions continue about narrow Main Street roadway
During Tuesday's Select Board meeting, board member Shahidul Mannan asked Town Manager Norman Khumalo for an explanation about the narrow roadway on the western portion of the Main Street Corridor Project. The town elected to widen the newly reconfigured roadway this...
Main Street Corridor Project update: Eastbound detour at Grove Street to be used as needed this week
As part of the Main Street Corridor Project this week, the eastbound detour from Grove Street to Maple Street to Hayden Rowe Street and back to Main Street will be used on an as-needed basis. Project-wide, the contractor will patch around structures and do a final...
Main Street Corridor Project update: Eastbound detours resume
As part of the Main Street Corridor Project this week, the eastbound detour from Pleasant Street to Maple Street to Hayden Rowe Street and back to Main Street will be in place Monday through Friday. The eastbound detour from Grove Street to Maple Street to Hayden Rowe...