Main Street Corridor Project update: Detour, alternating traffic lane this week

by | Jun 26, 2022 | News

A detour is planned for eastbound Main Street traffic on Monday and Wednesday this week due to work on the Main Street Corridor Project. The detour will send drivers from Main Street to Pleasant Street to Grove Street, which will return drivers to Main Street. On Tuesday, Thursday and Friday, there will be a single lane of alternating traffic in place.

Work this week includes full-depth excavation, which includes the removal of existing pavement and gravel to subgrade (approximately 22 inches), then the replacement and compaction of the gravel and the replacement of pavement, except for the final pavement, which will be done at the end of the project. Traffic will need to drive on compressed gravel for several weeks.

On Monday, removal of the existing pavement will begin on Main Street just past the Fire Station and move west toward Pleasant Street. Eastbound traffic will be detoured from Main to Pleasant to Grove Street.

On Tuesday, the work will continue from Pleasant Street to the westbound project limit and Wood Street with a single lane of alternating traffic in place.

On Wednesday, the removal of existing gravel will begin at Pleasant Street and move east toward the Fire Station. Eastbound traffic will be detoured from Main to Pleasant to Grove Street.

On Thursday, the removal of existing gravel will begin at the project westbound limit and Wood Street and continue east to Pleasant Street. A single lane of alternating traffic will be in place.

Working hours will be extended this week to 5 p.m. to allow all areas to be excavated by the end of day on Thursday. A single lane of alternating traffic will be in place for Friday. All work for the project is planned to be complete by noon on Friday, if possible, in advance of the July 4 weekend.

0 Comments

Related Articles

Saturday morning work scheduled for I-90/I-495 interchange ramps

The Massachusetts Department of Transportation announced that ramps at the Interstate 90/Interstate 495 interchange will close during the early morning on Saturday. Between 1-4 a.m. on Saturday, the I-495 northbound and southbound ramps (Exit 58) connecting to I-90...

MassDOT logo

Arrests/Police Log, April 1 edition

ARRESTS None this week. [Editor’s note: The Hopkinton Independent’s policy for the arrests section is not to include the names of individuals who have been arrested.]   POLICE LOG March 24 2:17 a.m. Officer Eva Cann made checks of Legacy Farms South. 6:53 a.m....

Hopkinton police cruiser

Water discoloration possible after hydrant test, well activations

The Water-Sewer Department conducted a required hydrant test near 66 Fruit Street on Tuesday morning that it warns could result in water discoloration. "We anticipate this flow test will cause discolored water in the test area and on the west side of town,"...

Fire hydrant
Key Storage 4.14.22