The town’s latest Main Street Corridor Project update released Friday shared that the transfer of services from the existing overhead systems to the new underground systems continues to make progress. Crown Castle has completed its work, and as of Dec. 16, Eversource...
Hopkinton Main Street Corridor Project
Main Street Corridor Project update: Utility work continues
The town’s latest Main Street Corridor Project update released Friday shared that utility companies will be on-site for work during the coming week. Dagle Electric will continue service cut-overs on the east side of the project. Affected abutters will be notified via...
Main Street Corridor Project update: Utility work continues
The town’s latest Main Street Corridor Project update released Friday shared that utility companies will be on-site for work during the coming week. Dagle Electric will continue service cut-overs on the east side of the project. Affected abutters will be notified via...
Main Street Corridor Project update: Utility work continues
The town’s latest Main Street Corridor Project update released Friday shared that utility work will continue over the next two weeks, with the exception of Nov. 28-29 in observance of the Thanksgiving holiday. Eversource will be on-site to work on underground services...
Main Street Corridor Project update: Town continues to wait for Verizon
The town’s latest Main Street Corridor Project update released Friday shared that Eversource will continue to perform underground work during the upcoming week. The town continues to await a schedule from Verizon to complete overhead utility transfers on the west side...
Main Street Corridor Project update: Eversource continues underground work
The town’s latest Main Street Corridor Project update released Friday shared that Eversource will continue to perform underground work during the upcoming week, with the exception of Monday’s Veterans Day holiday. The town also is awaiting a schedule from Verizon to...
Main Street Corridor Project update: Wall, walkway work continue
The town’s latest Main Street Corridor Project update released Friday shared that wall and walkway work will resume at 35 Main Street on Monday and Tuesday. Similar walkway work will commence at 77 Main Street on Tuesday and Wednesday . Miscellaneous work will be...
Main Street Corridor Project update: Sidewalk in front of Town Hall to be excavated Tuesday
The town’s latest Main Street Corridor Project update released Friday shared that A.F. Amorello & Sons, the project’s construction company, will be onsite on Tuesday to excavate the sidewalk in front of Town Hall for brick work installation. The entrance driveway...
Main Street Corridor Project update: Work continues on both ends of corridor
The town’s latest Main Street Corridor Project update released Friday explained that work will continue on both ends of the corridor during the upcoming week. Overhead utility line transfer work will continue on the west side of the project. On the east side of the...
Main Street Corridor Project update: Work progresses on both ends of corridor
The town’s latest Main Street Corridor Project update released Friday noted that work will continue on both ends of the corridor. Brick strip installation by A.F. Amorello & Sons, the project’s construction company, will continue during the upcoming week on the...
Main Street Corridor Project update: Brick strip installation continues along corridor
The town's latest Main Street Corridor Project update released Friday noted that brick strip installation by A.F. Amorello & Sons, the project’s construction company, will continue during the upcoming week. Drainage structures in front of Town Hall will be...
Main Street Corridor Project update: Painting repairs completed on mast arms throughout project
The town's latest Main Street Corridor Project update notes that Polar Vortex has completed painting the mast arms, the structures on which traffic lights are mounted, throughout the project. Polar Vortex’s crew has been painting the traffic poles, where paint was...
Main Street Corridor Project update: Preparation for brick installation expected to resume after Labor Day
The town on Friday issued an update on the Main Street Corridor Project, noting that preparation for brick installation is anticipated to begin after the Labor Day holiday. A.F. Amorello & Sons, the project’s construction company, is expected to return to on-site...
Main Street Corridor Project update: All 12 transformers installed
The town on Friday issued an update on the Main Street Corridor Project, announcing that all 12 transformers have been installed. The receipt of the transformers had been delayed for months by supply chain issues. After a push in June by Select Board chair Brian Herr,...
Main Street Corridor Project update: Brick installation to begin in late August after mock-up receives approval
The town on Friday issued an update on the Main Street Corridor Project, noting that the brick mock-up was approved so that work can be done to prepare for installation slated to begin in late August. The brick mock-up in front of Town Hall was completed on Aug. 12....
Main Street Corridor Project update: Progress made with transformer installation
The town on Friday issued an update on the Main Street Corridor Project, noting that the final six transformers of the 12 necessary to complete the project were received from Eversource. They are in the testing phase, and no issues are anticipated. Three of the six...
Main Street Corridor Project update: Utility line transfer work continues on project’s west side
The town on Friday issued an update on the Main Street Corridor Project. Overhead utility line work will continue on the west side of the project during the upcoming week, while work on underground utility connections from property lines to building foundations also...
Transformers set to arrive for Main Street Corridor Project after long delay
Town Manager Elaine Lazarus announced Monday afternoon that six of the 12 transformers needed to complete the underground installation of electrical wires for the Main Street Corridor Project will be arriving this week from Eversource. After months of delay due to...
Commission on Disability airs accessibility concerns about Main Street Corridor Project
The Commission on Disability at its meeting Monday night discussed concerns about accessibility with Michelle Murdock, the professional project specialist for the town on the Main Street Corridor Project. Murdock first announced some “awesome news” about the project....
Main Street Corridor Project update: Utility line transfer work continues on project’s west side
The town on Friday issued an update on the Main Street Corridor Project. Overhead utility line work will continue on the west side of the project during the upcoming week. Polar Vortex’s painting crew will continue its work on the traffic poles, repairing peeling...